1962 March 8
1962 March 15-16 - First monthly meeting of the Apollo design and review team to survey NAA's progress
Charles W. Frick, Manager of the MSC Apollo Spacecraft Project Office, together with Maxime A. Faget, Charles W. Mathews, Christopher C. Kraft, Jr., John B. Lee, Owen E. Maynard, and Alan B. Kehlet of MSC and George M. Low of the NASA Office of Manned Space Flight, visited NAA at Downey, Calif. This was the first monthly meeting of the Apollo design and review team to survey NAA's progress in various areas, including the Apollo spacecraft heatshield, fuel cells, and service module.
1962 April
1962 May - Study of integrating the Apollo fuel cell and environmental control heat rejection systems
NAA evaluated the possibility of integrating the fuel cell and environmental control system heat rejection into one system. The integrated system proved to be unsatisfactory, being 300 pounds heavier and considerably more complex than the two separate systems. A preliminary design of separate fuel cell radiators, possibly located on the service module, was started by NAA.
1962 July 16
1962 August
1962 September - Three fuel cells to supply power for Apollo
MSC reported that the three liquid-hydrogen-liquid-oxygen fuel cells would supply the main and emergency power through the Apollo mission except for the earth reentry phase. Two of the fuel cells would carry normal electrical loads and one would supply emergency power. Performance predictions had been met and exceeded in single-cell tests. Complete module tests would begin during the next quarter. The liquid-hydrogen liquid-oxygen reactants for the fuel cell power supply were stored in the supercritical state in spherical pressure vessels. A recent decision had been made to provide heat input to the storage vessels with electrical heaters rather than the water-glycol loop. Three zinc-silver oxide batteries would supply power for all the electrical loads during reentry and during the brief periods of peak loads. One of the batteries was reserved exclusively for the postlanding phase. Eagle Picher Company, Joplin, Mo., had been selected in August as subcontractor for the batteries.
1963 December 19
1964 January 15 - First Apollo fuel cell delivered by Pratt and Whitney
The first fuel cell module delivered by Pratt and Whitney Aircraft to North American was started and put on load. The module operated normally and all test objectives were accomplished. Total operating time was four hours six minutes, with one hour at each of four loads-20, 30, 40, and 50 amperes. The fuel cell was shut down without incident and approximately 1,500 cubic centimeters (1.6 quarts) of water were collected.
1964 February 17 - During a lunar mission, fuel cells in the Apollo CSM would produce 220 liters of potable water
MSC announced that, during a 14-day lunar mission, fuel cells in the Apollo CSM would produce about 220 liters (60 gallons) of potable water while furnishing power to operate the electronic equipment.
1964 February 20-26 - Three tests on the Apollo CSM fuel cell
North American conducted three tests (4, 20, and 88 hours) on the CSM fuel cell. The third ended prematurely because of a sudden drop in output. (Specification life on the modules was 100 hours.) During this same week, Pratt and Whitney Aircraft tested a LEM-type fuel cell for 400 hours without shutdown and reported no leaks.
1964 October 16-November 15 - Three Apollo fuel cells operated in a simulated space vacuum
Three Pratt and Whitney fuel cells were operated in a simulated space vacuum at North American for 19, 20, and 21 hours. This was the first time three cells were operated as an electrical power generating subsystem.
1964 November 10 - First firing of the service propulsion system engine
Joseph G. Thibodaux, Jr., MSC Propulsion and Power Division, reported at an Apollo Engineering and Development technical management meeting that the first J-2 firing of the service propulsion system engine was conducted at White Sands Missile Range (WSMR). Two fuel cell endurance tests of greater than 400 hours were completed at Pratt and Whitney. MSC would receive a single cell for testing during the month.
1965 March 29-April 4
1965 April 16-May 15
1965 June 16
1966 January 8-11 - First Apollo fuel cell system test at White Sands
The first fuel cell system test at White Sands Test Facility was conducted successfully. Primary objectives were: 1 to verify the capability of the ground support equipment and operational checkout procedure to start up, operate, and shut down a single fuel cell power plant; and 2 to evaluate fuel cell operations during cold gimbaling of the service propulsion engine.
1966 November 4 - Concern over the extensive damage to Apollo fuel cell modules from operational errors
NASA Apollo Program Director Samuel C. Phillips indicated his concern to MSC over the extensive damage to a number of fuel cell modules from operational errors during integrated system testing. Phillips pointed out that in addition to the added cost there was a possible impact on the success of the flight program. He emphasized the importance of standardizing the procedures for fuel cell activation and shutdown at North American Aviation, MSC, and KSC to maximize learning opportunities.
1967 May 31 - Apollo fuel cell system failure actions
George M. Low told Joseph N. Kotanchik, Chief of MSC's Structures and Mechanics Division, that actions were pending on Pratt & Whitney pressure vessel failures. The pressure vessels were used in the Apollo fuel cell system. Kotanchik had spelled out a list of problem areas in connection with both the vessels and management interface between MSC and principal contractor North American Aviation, and between North American and its subcontractor Pratt & Whitney.
1970 April 11 - Apollo 13
Apollo 13 (AS-508) was launched from Pad A, Launch Complex 39, KSC, at 2:13 p.m. EST April 11, with astronauts James A. Lovell, Jr., John L. Swigert, Jr., and Fred W. Haise, Jr., aboard. The spacecraft and S-IVB stage entered a parking orbit with a 185.5-kilometer apogee and a 181.5-kilometer perigee. At 3:48 p.m., onboard TV was begun for five and one-half minutes. At 4:54 p.m., an S-IVB burn placed the spacecraft on a translunar trajectory, after which the CSM separated from the S-IVB and LM Aquarius. (The crew had named lunar module 7 Aquarius and CSM 109 Odyssey.) The CSM then hard-docked with the LM. The S-IVB auxiliary propulsion system made an evasive maneuver after CSM/LM ejection from the S-IVB at 6:14 p.m. The docking and ejection maneuvers were televised during a 72-minute period in which interior and exterior views of the spacecraft were also shown. At 8:13 p.m. EST a 217-second S-IVB auxiliary propulsion system burn aimed the S-IVB for a lunar target point so accurately that another burn was not required. The S-IVB/IU impacted the lunar surface at 8:10 p.m. EST on April 14 at a speed of 259 meters per second. Impact was 137.1 kilometers from the Apollo 12 seismometer. The seismic signal generated by the impact lasted 3 hours 20 minutes and was so strong that a ground command was necessary to reduce seismometer gain and keep the recording on the scale. The suprathermal ion detector experiment, also deployed by the Apollo 12 crew, recorded a jump in the number of ions from zero at the time of impact up to 2,500 shortly thereafter and then back to a zero count. Scientists theorized that ionization had been produced by 6,300 K to 10,300 K (6,000 degrees C to 10,000 degrees C) temperature generated by the impact or that particles had reached an altitude of 60 kilometers from the lunar surface and had been ionized by sunlight. Meanwhile back in the CSM/LM, the crew had been performing the routine housekeeping duties associated with the period of the translunar coast. At 30:40 ground elapsed time a midcourse correction maneuver took the spacecraft off a free-return trajectory in order to control the arrival time at the moon. Ensuring proper lighting conditions at the landing site. The maneuver placed the spacecraft on the desired trajectory, on which the closest approach to the moon would be 114.9 kilometers. At 10:08 p.m. EST April 13, the crew reported an undervoltage alarm on the CSM main bus B, rapid loss of pressure in SM oxygen tank No. 2, and dropping current in fuel cells 1 and 3 to a zero reading. The loss of oxygen and primary power in the service module required an immediate abort of the mission. The astronauts powered up the LM, powered down the CSM, and used the LM systems for power and life support. The first maneuver following the abort decision was made with the descent propulsion system to place the spacecraft back in a free-return trajectory around the moon. After the spacecraft swung around the moon, another maneuver reduced the coast time back to earth and moved the landing point from the Indian Ocean to the South Pacific.
1970 April 19 - Apollo 13 Review Board panels established
To support the Apollo 13 Review Board, an MSC Apollo 13 Investigation Team, headed by Scott H. Simpkinson, was established with the several panels. Spacecraft incident investigation, flight crew observations, flight operations and network ; photograph handling, processing, and cataloging ; corrective action study and implementation for the CSM, LM, and government-furnished equipment; related system evaluation; reaction processes in high-pressure fluid systems; high-pressure oxygen system survey; public affairs; and administration, communications, and procurement.
1970 November 24 - MSC Director Robert R Gilruth reported MSC actions on the Apollo 13 Review Board recommendations
MSC Director Robert R. Gilruth reported MSC actions on the Apollo 13 Review Board recommendations. - Fan motors had been removed from oxygen storage tanks in the service modules; the electrical leads had been encased in stainless steel sheaths with hermetically sealed headers and had been shielded from contact with the remaining Teflon parts. - The modified cryogenic oxygen storage system had been subjected to a comprehensive recertification program developed in close coordination by North American Rockwell, Beech Aircraft Corp., and NASA. Requirements were founded on environmental as well as operational factors necessary to prove design capability. - No major changes had been made in the caution and warning system. - The LM and CSM consumables and emergency equipment had been reviewed to determine any design changes required to provide a safe return from lunar orbit in the event of a service module cryogenic-oxygen-supply loss. Three design changes were made in the CSM related to the oxygen tanks, an LM descent battery, and a water storage system in the CM. - MSC had made special tests and analyses to understand the Apollo 13 accident better. The testing had reaffirmed the conclusions reached by the Apollo 13 Review Board. - Significant anomalies in critical subsystems during final preparation for launch would be analyzed and resolved with authorized and documented corrective action in much the same manner as employed during the missions. An Apollo Program Directive for identification and resolution of significant failures and anomalies had been issued. - A thorough reexamination of all spacecraft, launch vehicle, and ground systems containing high-density oxygen and other strong oxidizers was being made to identify and evaluate potential combustion hazards. - Additional research was being conducted on materials compatibility, ignition, and combustion in strong oxidizers at various gravity levels and on the characteristics of supercritical fluids. Arc-ignition tests of the Apollo 14 oxygen-storage-system materials in both normal and overstressed modes indicated a positive margin of safety. - MSC had organized a system-by-system task team effort and made comprehensive reassessments of each subsystem. Design and qualification of each subsystem was reaffirmed as adequate for current ground test and mission requirements with the exception of a heatshield blowout plug for dumping reaction-control-subsystem propellant for launch aborts.
Contact us with any corrections, additions, or comments.
Conditions for use of drawings, pictures, or other materials from this site..
To contact astronauts or cosmonauts.
© Mark Wade, 1997 - 2008 except where otherwise noted.
|
|