1962 November - Study of Apollo CSM-LEM transposition and docking
North American completed a study of CSM-LEM transposition and docking. During a lunar mission, after the spacecraft was fired into a trajectory toward the moon, the CSM would separate from the adapter section containing the LEM. It would then turn around, dock with the LEM, and pull the second vehicle free from the adapter. The contractor studied three methods of completing this maneuver: free fly-around, tethered fly- around, and mechanical repositioning. Of the three, the company recommended the free fly-around, based on NASA's criteria of minimum weight, simplicity of design, maximum docking reliability, minimum time of operation, and maximum visibility. Also investigated was crew transfer from the CM to the LEM, to determine the requirements for crew performance and, from this, to define human engineering needs. North American concluded that a separate LEM airlock was not needed but that the CSM oxygen supply system's capacity should be increased to effect LEM pressurization. On November 29, North American presented the results of docking simulations, which showed that the free flight docking mode was feasible and that the 45-kilogram (100-pound) service module (SM) reaction control system engines were adequate for the terminal phase of docking. The simulations also showed that overall performance of the maneuver was improved by providing the astronaut with an attitude display and some form of alignment aid, such as probe.
1963 January 30
1963 March 11
1963 March 14 - Bidders' conference for Apollo LEM mechanically throttled descent engine
A bidders' conference was held at Grumman for a LEM mechanically throttled descent engine to be developed concurrently with Rocketdyne's helium injection descent engine. Corporations represented were Space Technology Laboratories; United Technology Center, a division of United Aircraft Corporation; Reaction Motors Division, Thiokol Chemical Corporation; and Aerojet-General Corporation. Technical and cost proposals were due at Grumman on April 8.
1963 April - Apollo LEM reaction control system (RCS) to be equipped with dual interconnected tanks
Grumman recommended that the LEM reaction control system (RCS) be equipped with dual interconnected tanks, separately pressurized and employing positive expulsion bladders. The design would provide for an emergency supply of propellants from the main ascent propulsion tanks. The RCS oxidizer to fuel ratio would be changed from 2.0:1 to 1.6:1. MSC approved both of these changes.
1963 July 19 - Marquardt begins development of the Apollo LEM reaction control thrusters
Grumman directed the Marquardt Corporation to begin development of the LEM reaction control system thrusters. Negotiations had begun on March 11 on the definitive subcontract, a cost-plus-incentive-fee type with a total estimated cost of $10,871,186.
1963 August - Full-scale cardboard model of the Apollo LEM
Grumman built a full-scale cardboard model of the LEM to aid in studying problems of cockpit geometry, specifically the arrangement of display panels. This mockup was reviewed by MSC astronauts and the layout of the cockpit was revised according to some of their suggestions. Also Grumman reported that a preliminary analysis showed the reaction control system plume heating of the LEM landing gear was not a severe problem. (This difficulty had been greatly alleviated by the change from five to four landing legs on the vehicle.
1963 November 13-14 - Means for reducing the weight of the Apollo LEM
After careful study, Grumman proposed to MSC 15 possible means for reducing the weight of the LEM. These involved eliminating a number of hardware items in the spacecraft; two propellant tanks in the vehicle's ascent stage and consequent changes in the feed system; two rather than three fuel cells; and reducing reaction control system propellants and, consequently, velocity budgets for the spacecraft. If all these proposed changes were made, Grumman advised, the LEM could be lightened significantly, perhaps by as much as 454 kilograms (1000 pounds).
1963 December 21 - MSC defined the Apollo LEM terminal rendezvous maneuvers
MSC defined the LEM terminal rendezvous maneuvers. That phase of the mission would begin at a range of 9.3 kilometers (five nautical miles) from the CSM and terminate at a range of 152.4 meters (500 feet). Before rendezvous initiation, closing velocity should be reduced to 61 meters (200 feet) per second by use of the ascent engine. The reaction control system should be used exclusively thereafter.
1964 January 8
1964 January 27
1964 February 20-26
1964 March 12
1964 October 8-15 - Configuration established of the reaction control system engines
MSC established the configuration of the reaction control system engines for both the service module (SM) and the LEM, and informed North American and Grumman accordingly. The Center also directed North American to propose a design for an electric heater that would provide thermal control in lunar orbit and during contingency operations. The design would be evaluated for use in Block I spacecraft as well.
1964 October 8 - Contract for the Apollo LEM attitude translation control assembly
Radio Corporation of America's (RCA) Aerospace Systems Division received a 9 million contract from Grumman for the LEM attitude translation control assembly (ATCA). The ATCA, a device to maintain the spacecraft's attitude, would fire the reaction control system motors in response to signals from the primary guidance system.
1964 October 12 - Apollo CSM-LM active docking interfaces discussed
At a North American-Grumman interface meeting on September 23-24, two possible relative role alignments for CSM-active docking were agreed upon. The major item blocking final selection was the effect of the SM's reaction control system engines upon the LEM antennas. ASPO requested Grumman to investigate the problem, to analyze the design penalties of the two-attitude docking mode, and to report any other factors that would influence the final attitude selection.
1964 December 7
1964 December 9 - Criteria for firing times of the SM RCS
Grumman received from Houston criteria for firing times of the SM reaction control system (RCS). These served as a basis for the design of the LEM's steerable antenna. The thermal design proposed by Dalmo-Victor, the vendor, appeared feasible to watchdogs in MSC's Instrumentation and Electronic Systems Division. On the other hand, the unbalanced wind torque produced by the RCS engines was still a problem. RCA and Dalmo-Victor's estimates of the amount of torque varied considerably, and Grumman consequently undertook a study of this problem.
1964 December 11 - Updated criteria for the Apollo LEM's landing gear
From MSC, Grumman received updated criteria to be used in the design of the LEM's landing gear. The gear must be designed to absorb completely the landing impact; it must also provide adequate stability for the vehicle under varying surface conditions, which were spelled out in precise detail.) Maximum conditions that MSC anticipated at touchdown were: vertical velocity - 3.05 m (10 ft) per sec horizontal velocity - 1.22 m (4 ft) per sec spacecraft attitude pitch - 3 degrees roll - 3 degrees yaw - random attitude rates - 3 degrees per sec At touchdown, all engines (descent and reaction control would be off. "It must be recognized," MSC emphasized, "that the vertical and horizontal velocity values . . . are also constraints on the flight control system."
1964 December 15-16 - Thermal-demanded weight increases for the Apollo LEM's steerable antenna
Dalmo-Victor studied thermal-demanded weight increases for the LEM's steerable antenna. Investigators reported to Grumman and RCA that, in the plume of the CSM's reaction control engines, 1.18 kg (2.5 lbs) was necessary merely for the survival of the antenna; another 1.18 kg would be required for tracking during this impingement.
1964 December 21 - Thermal status of antennas for the Apollo CSM and LEM spacecraft
The Structures and Mechanics Division (SMD) summarized the thermal status of antennas for the Apollo spacecraft (both CSM and LEM). Generally, most troubles stemmed from plume impingement by the reaction control or radiation from the service propulsion engines. These problems, SMD reported, were being solved by increasing the weight of an antenna either its structural weight or its insulation; by shielding it from the engines' exhaust; by isolating its more critical components; or by a combination of these methods.
1965 January 18 - Low-burst factor for the gaseous helium tanks on the Apollo LEM approved
The Structures and Mechanics Division approved a low-burst factor for the gaseous helium tanks on the LEM (as recommended by Grumman). This change permitted a substantial lightening of the spacecraft's propulsion systems: descent 45 kg (99 lbs); ascent, 13 kg (29 lbs); reaction control, 2.3 kg (5 lbs).
1965 January 28-February 4 - Device to detect failures in the reaction control system (RCS) for Block I Apollo CSMs cancelled
MSC canceled plans (originally proposed by North American) for a device to detect failures in the reaction control system (RCS) for Block I CSMs. This was done partly because of impending weight, cost, and schedule penalties, but also because, given an RCS failure during earth orbit, the crew could detect it in time to return to earth safely even without the proposed device. This action in no way affected the effort to devise such a detection system for the Block II CSM or the LEM, however.
1965 March 15 - Descent engine cutoff light during the Apollo LEM lunar touchdown
An evaluation was made of the feasibility of utilizing a probe-actuated descent engine cutoff light during the LEM lunar touchdown maneuver. The purpose of the light, to be actuated by a probe extending 0.9 m (3 ft) beyond the landing gear pads, was to provide an engine cutoff signal for display to the pilot. Results of the study indicated at least 20 percent of the pilots failed to have the descent engine cut off at the time of lunar touchdown. The high percentage of engine-on landings was attributed to - poor location of the cutoff switch,
- long reaction time (0.7 sec) of the pilot to a discrete stimulus (a light), and
- the particular value of a descent rate selected for final letdown (4 ft per sec).
It was concluded that a 0.9-m (3-ft) probe would be adequate to ensure pilot cutoff of the descent engine before touchdown provided the pilot reaction time could be reduced to 0.4 sec or less by improving the location of the cutoff switch.
1965 April 7
1965 April 15-22
1965 April 22
1965 June 16-23
1965 July 23 - Significant hardware Apollo changes
MSC authorized North American to make a number of significant hardware changes. - Place filters in the propellant lines of the SM's reaction control system. - Cease all work on an extravehicular probe (responsibility which MSC now assumed). - Delete from the stabilization and control system (SCS) of all Block II CSMs the hybrid thrust vector control apparatus. (This change reduced the functional capability of the SCS and simplified the system's interface with the guidance and navigation system.) - Delete the HE orbital antenna from CSMs 012, 014, and all Block II spacecraft. - Change the propellant mixture in the service propulsion system of Block II spacecraft. The service propulsion engine would be modified, which would require additional developmental and qualification testing. - Go ahead on thermal coating on the adapter (to achieve the desired thermal environment for the LEM during boost).
1965 August 29-September 4 - Several important activities were noted during Apollo reporting period
Several important activities were noted during the reporting period: (1) Qualification of the new reefing line cutters was progressing satisfactorily and scheduled for completion in October 1965. (The cutter had been used successfully on the last two earth landing system tests conducted at El Centro); (2) the helium storage tank for the LEM reaction control subsystem successfully passed qualification tests; and (3) the Aero Spacelines' new aircraft, "Super Guppy," made its maiden flight from Van Nuys, Calif., to Mojave Airfield, Calif. The new aircraft had the capability of airlifting the spacecraft-LEM-adapter as well as providing vital backup for the "Pregnant Guppy" aircraft.
1965 August
1965 September 27 - Problem of Apollo back contamination of earth discussed
Officials from the U.S. Public Health Service (PHS) and the Department of Agriculture met at MSC to discuss informally the problem of back contamination. They listened to briefings on the mission profile for Apollo; reentry heating rates; present thinking at the Center on the design of the Lunar Sample Receiving Station (LSRS); and MSC's plans (none) for quarantining the astronauts. James Goddard, Assistant Surgeon General in PHS, presented three broad areas of concern: - quarantine procedures and accommodations inside the LSRS for both astronauts and technicians;
- quarantine facilities aboard the recovery ships; and
- the need to gather samples before the moon's surface was contaminated by the astronauts or the LEM's atmosphere.
These matters were discussed in some detail. MSC's failure to plan for the astronauts' return, and Goddard's ideas on what procedures were needed, provoked "very extended and somewhat heated" discussions. It was generally agreed that Apollo astronauts could not entirely avoid lunar contaminants: the level of contamination inside the spacecraft's cabin, although low, nonetheless would be "significant." MSC then asked, hypothetically, what PHS's reaction would be if Apollo astronauts were recovered and returned in much the same manner that Gemini crews were. The representative from PHS's Foreign Quarantine Division replied "emphatically" that, in such a case, those crews would not be allowed back in the country.On October 15, Lawrence B. Hall, Planetary Quarantine Officer in NASA's Office of Space Science and Applications, summarized for Deputy Administrator Hugh L. Dryden the September 27 meeting, and recommended that such informal discussions continue. "I believe," he told Dryden, "that . . . the Manned Spacecraft Center is more fully aware of the point of view of the regulatory agencies on this matter. Unfortunately, the regulatory agencies still do not understand the reasons for the Manned Spacecraft Center's reluctance to face this problem."
1965 November 15
1966 August 22 - Surveyor vernier engine to be fired after landing
MSC Director Robert R. Gilruth requested of Jet Propulsion Laboratory Director William H. Pickering that JPL fire the Surveyor spacecraft's vernier engine after the Surveyor landed on moon, to give insight into how much erosion could be expected from an LM landing. The LM descent engine was to operate until it was about one nozzle diameter from landing on the lunar surface; after the Surveyor landed, its engine would be about the same distance from the surface. Gilruth told Pickering that LaRC was testing a reaction control engine to establish surface shear pressure forces, surface pressures, and back pressure sources, and offered JPL that data when obtained.
1966 December 26 - Extravehicular activity on the Apollo AS-503 mission
Donald K. Slayton said there was some question about including extravehicular activity on the AS-503 mission, but he felt that, to make a maximum contribution to the lunar mission, one period of EVA should be included. Slayton pointed out that during the coast period (simulating lunar orbit) in the current flight plan the EVA opportunity appeared best between hour 90 and hour 100.
Two primary propulsion system firings would have been accomplished and the descent stage of the LM would still be attached. Slayton specified that EVA should consist of a crewman exiting through the LM forward hatch and making a thorough orbital check of the LM before reentering through the same hatch. He said EVA on AS-503 would provide: - flight experience and confidence in LM environmental-control-system performance during cabin depressurization; - flight confidence in the Block II International Latex Corp. pressure garment assemblies; - orbital time-line approximation of cabin depressurization times, forward hatch operation, flight crew egress procedures, and LM entry following a simulated lunar EVA; - visual inspection and photography of LM landing gear for possible damage during withdrawal from the S-IVB stage; - external inspection and photography of the LM to record window and antenna contamination caused by SLA panel pyrotechnic deployment; - inspection and photography of descent engine skirt and adjacent areas for evidence of damage from two descent propulsion system firings; - inspection and photography of possible damage to the upper LM caused by the SM reaction control system during withdrawal; - possible additional data regarding EVA metabolic rates, etc., as applied to the Block II pressure garment assembly; and - additional orbital confidence in the portable life support system operational procedures.
1967 May 29 - Bare copper wires exposed to glycol/water found to ignite in Apollo oxygen cabin environement
W. R. Downs, Special Assistant for Advanced Systems, MSC Structures and Mechanics Division, discovered that bare or defectively insulated silver-covered copper wires exposed to glycol/water solutions would ignite spontaneously and burn in oxygen. Copper wire or nickel-covered copper wire under identical conditions did not ignite. The laboratory results were confirmed in work at the Illinois Institute of Technology. In a June 13 memorandum, the Chief of the Structures and Mechanics Division recommended that if additional testing verified that nickel-coated wires were free of the hazard, consideration should be given to an in-line substitution of nickel-coated wires for silver-coated wires in the LM. It was understood that the Block II CSM already had nickel-coated wires. In a June 20 memo to the ASPO Manager, the Director of Engineering and Development pointed out that silver-plated pins and sockets in connectors would offer the same hazards. He added that Downs had also identified a chelating agent that would capture the silver ion and apparently prevent the reaction chain. In a July 24 memorandum, ASPO Manager George Low said that, in view of recent spills of ethylene glycol and water mixtures, spacecraft contractors North American Aviation and Grumman Aircraft Engineering had been directed to begin actions immediately to ensure that a fire hazard did not exist for the next manned spacecraft. Actions were to include identification of the location of silver or silver-covered wires and pins and of glycol spills.
1968 February 20
1968 June 10 - Important Apollo events
In his weekly progress report to the NASA Administrator, Deputy Administrator for Manned Space Flight George E. Mueller cited several important Apollo events during the first week of June. - On June 1, technicians at MSC completed thermal-vacuum testing on LTA-8 to support LM-3, including 45% hours of manned testing. All spacecraft systems functioned normally, and preliminary results indicated that all significant test objectives had been realized. - Engineers and technicians at KSC completed receiving inspection of CSM 101 on June 3. That inspection revealed fewer discrepancies than had been present on any other spacecraft delivered to the Cape. Pre-mate inspection of CM 101 also was completed, as were leakage and functional tests on the electrical power and reaction control systems. SM 101 was in the altitude chamber being prepared for combined systems testing.
1968 August 7 - George Low promotes idea of flying Apollo 8 as a lunar orbit mission without the Lunar Module
On August 7, Low asked MSC's Director of Flight Operations Christopher C. Kraft, Jr., to look into the feasibility of a lunar orbit mission for Apollo 8 without carrying the LM. A mission with the LM looked as if it might slip until February or March 1969. The following day Low traveled to KSC for an AS-503 review, and from the work schedule it looked like a January 1969 launch.
Events and the situation during June and July had indicated to Low that the only way for the "in this decade" goal to be attained was to launch the Saturn 503/CSM 103 LM-3 mission in 1968. During June and July the projected launch slipped from November to December, with no assurance of a December launch. Later, Low recalled "the possibility of a circumlunar or lunar orbit mission during 1968, using AS-503 and CSM 103 first occurred to me as a contingency mission." During the period of July 20-August 5, pogo problems that had arisen on Apollo 6 seemed headed toward resolution; work on the CSM slowed, but progress was satisfactory; delivery was scheduled at KSC during the second week in August and the spacecraft was exceptionally clean. The LM still required a lot of work and chances were slim for a 1968 launch.
1971 October 6-7 - Apollo 15 anomalies
Major items of discussion during the Manned Space Flight Management Council meeting in Washington were the Apollo 15 anomalies. These included parachute collapse during landing, lunar module descent battery, lunar surface drill, and steering mechanism on the LRV. Also discussed were the Apollo 16 preparations and the feasibility of TV coverage of the lunar rover during traverse. The most likely cause of the parachute collapse was damage from burning raw RCS fuel (monomethyl hydrazine) being expelled during depletion firing. Corrective action included landing with reaction control system propellants on board for a normal landing and biasing the propellant load to a slight excess of oxidizer and increasing the time delay inhibiting the rapid propellant dump, to avoid fuel contacting the parachute riser and suspension lines during low-altitude-abort land landings.
Contact us with any corrections, additions, or comments.
Conditions for use of drawings, pictures, or other materials from this site..
To contact astronauts or cosmonauts.
© Mark Wade, 1997 - 2008 except where otherwise noted.
|
|