The detailed schedule was as follows:
UR-500/L1 flights
Phase I:
Vehicle 2P - Complete manufacture: 1966 December; Launch: 1967 February (delayed to March 10)
Vehicle 3P - Complete manufacture: 1967 February; Launch: 1967 March
Phase II:
Vehicle 4L - Complete manufacture: 1967 February; Launch: 1967 May
Vehicle 5L - Complete manufacture: 1967 March; Launch: 1967 June
Phase III:
Vehicle 6L - Complete manufacture: 1967 April; Launch: 1967 July
Vehicle 7L - Complete manufacture: 1967 May; Launch: 1967 August
Vehicle 8L - Complete manufacture: 1967 June; Launch: 1967 August
Vehicle 9L - Complete manufacture: 1967 July; Launch: 1967 September
Vehicle 10L - Complete manufacture: 1967 August; Launch: 1967 September
Vehicle 11L - Complete manufacture: 1967 August; Launch: 1967 October
Vehicle 12L - Complete manufacture: 1967 September; Launch: 1967 October
Vehicle 13L - Complete manufacture: 1967 September (back-up)
N1 flights
Phase I:
Vehicle 3L - Complete manufacture: 1967 June; Launch: 1967 September
Vehicle 4L - Complete manufacture: 1967 December (back-up)
Phase II:
Vehicle 5L - Complete manufacture: 1967 October; Launch: 1967 December
Vehicle 6L - Complete manufacture: 1967 December; Launch: 1968 February
Phase III:
Vehicle 7L - Complete manufacture: 1968 February; Launch: 1968 April
Vehicle 8L - Complete manufacture: 1968 April; Launch: 1968 June
Phase IV:
Vehicle 9L - Complete manufacture: 1968 June; Launch: 1968 August
Phase V:
Vehicle 10L - Complete manufacture: 1968 August; Launch: 1968 Sep
Vehicle 11L - Complete manufacture: 1968 October (back-up)
Vehicle 12L - Complete manufacture: 1968 December (back-up)