Korolev felt that if he had the full support of the Communist Party, the military, and industry he could achieve this goal, and this decree ordered such support. The USSR would be first on the moon. But in truth the draft project behind the decree had not solved all of the technical problems, or provided a solution on how to achieve the required payload on either the booster or spacecraft side. New technology features required for success of the scheme included an advanced guidance system in the N1 third stage equipment bay, the enormous fuel tanks in the N1 first stage, and the Lox/LH2 fuel cells needed for the LOK lunar orbiter. But the real technical problem with the N1-L3 design was the total lack of any weight growth reserve. Even thought the systems had not even been developed yet, engineers were fighting over tens of grams in their weight allocations, let alone the kilograms normally at issue.
Development of Korolev's Soyuz A-B-V, a competing circumlunar project, was evidently still authorised, although it duplicated Chelomei's LK-1.
Finally Korolev gets to the purpose of the secret meeting. He wants Feoktistov to be aboard Voskhod 1, despite the opinion of Kamanin and the physicians. Kamanin reiterates that the most qualified crew would be Komarov, Volynov, and Lazarev; and if he gives in on Feoktistov, then Komarov, Feoktistov, Lazarev. But Korolev is opposed to Lazarev, and insists that the crew should be Komarov, Feoktistov, and Yegorov. From Kamanin's point of view this is flying a space mission with two invalids aboard. Lazarev is a qualified and fit flight surgeon, a qualified pilot as well as a physician with 15 years of research experience in aviation medicine. Korolev is adamant that the two passengers should be civilian, not military. No agreement is possible.
After the death of Korolev in January, a letter was sent to the Central Committee requesting that Mishin be appointed director of OKB-1. Ustinov tried to line up support for Mishin, but by the time of the first first Saturn IB orbital flight on 26 February 1966, no decision had been made. America was progressing on the path to the moon, but Russia was stalled. An alternate that had been considered was Sergei Okhapkin, another Deputy Chief Designer at TsKBEM. But Okhapkin knew only spacecraft, he had never developed complete launch-booster-spacecraft systems. By the time Mishin was appointed, it was clear that the race was lost. The American's planned their first Saturn V launch in September 1967 and their first manned flight in 1968. Mishin could not expect trials of the LK lunar lander until 1969 at the earliest. There were insufficient funds allocated, and the schedule had no allowance for test flight failures. Ustinov, Morozhin, and Keldysh pointed fingers as to who had presented such unrealistic schedules to the Politburo. Keldysh now supported unmanned robot lunar landers in development by Babakin. Even these would not land until 1970, allowing three years of flight trials to achieve reliability. Khrushchev, it seemed, was to blame for such enormous unaffordable projects. This in turn put Ustinov in danger, as Khrushchev's point man for space.
Rudenko agrees with Kamanin's plan, except he urges him to assign more cosmonauts to the Soyuz 7K-OK group, and include OKB-1 cosmonauts in the 7K-OK, L1, and L3 groups, and Academy of Science cosmonauts in the L1 and L3 groups.
These cosmonaut assignments were in constant flux, and many cosmonauts were assigned to train for more than one program - resulting in multiple claims in later years that 'I was being trained for the first moon flight'.
Serial # Mission Date
2P Develop Block D stage Feb or Mar 67
3P same Mar 67
4L Unmanned lunar flyby May 67
5L Unmanned lunar flyby Jun 67
6L Manned lunar flyby Jun or Jul 67
7L&8L Manned lunar flybys Aug 67
9L&10L Manned lunar flybys Sep 67
11L&12L Manned lunar flybys Oct 67
13L Reserve spacecraft
N1-3L
Serial # Mission Date
3L Develop LV & Blocks G&D Sep 67
4L Reserve
5L LOK/LK unmanned Dec 67
6L LOK/LK unmanned Feb 68
7L Manned LOK/unmanned LK Apr 68
8L Manned LOK/unmanned LK Jun 68
9L Piloted LOK/unmanned LK
with LK landing on moon Aug 68
10L First men land on moon Sep 68
11L Reserve
12L Reserve
Kamanin's personal opinion of this schedule - manned L1 flights may occur before the end of 1967, but there will be no lunar landing until 1969.Beregovoi is to be named commander of the Gagarin Centre. Gagarin himself was being prepared for the job, but his death in a plane crash ended that plan. The other cosmonauts are not ready for command. The centre desperately needs the two planned L3 trainers: the TBK-150 and Volchuk. Kamanin has been jerked around for four months on the issue. Even if the simulators were delivered, he would still need 2 million roubles and an additional 30 to 40 staff to install and operate them.
Keldysh proposed that further work on the L1 be abandoned, and Proton boosters instead be used to launch the Ye-8-5 lunar soil return robot spacecraft being developed by Babakin. Babakin had been accelerating this programme since the beginning of 1968 with the support of Keldysh, even though it would only return around 100 g of lunar soil, versus the tens of kilograms the Apollo manned flights would return. However it now offered an interesting possibility - he proposed obtaining lunar soil and returning it to earth before an American manned landing. The government's organs of mass communication would say that the Soviet Union's lunar program only consisted of robot probes, emphasising that his was much safer and that Russia would never risk it's citizen's lives for mere political sensation. Additional Details: here....
On one of these August 1969 days, three of Chelomei's TsKBM engineers came to the office of Mishin's deputy, Chertok, with a plan to get a space station orbited before the American Skylab. They wanted a collaboration between the two competing design bureaux. Their plan was to take an Almaz spaceframe, install Soyuz systems, add a new docking tunnel with a hatch to reach the interior, and presto - a space station was finished. Tentative discussions with potential allies within Chelomei's design bureau found support there as well. The DOS 'long-duration orbiting station' was the result of this 'conspiracy'.
In any event these consideations were simply ignored. Feoktistov was present at a party meeting with Keldysh, Afanasyev, Tyulin, Serbin, and the Ministry of Defence's party cell: Strogonov, Kravtsev, and Popov. Keldysh was mainly worried how the project would affect the N1, but was reassured that the N1 had a dedicated work force, and the L3 lunar lander spacecraft engineers and workers that would work on DOS were currently idle and had no part of that work. It was finally decided to go ahead with the DOS no earlier than January, to allow time for Ministry Decrees, approval of a work plan by the VPK, preparation of a decree for signature by the Central Committee of the Communist Party and the Soviet Ministers. Work began on the project in December 1969 under the initial auspices of the Academy of Sciences. Additional Details: here....
Ustinov supported presentation of the DOS concept to the Central Committee. Chelomei categorically opposed DOS and was trying to kill it through military channels. But the allure of an '18 month' station - one which would not only beat the American Skylab, but be in space in time for the 24th Party Congress - seemed too alluring. Mishin also rejected DOS, but deputies at both design bureaux supported the concept and were eager to proceed.
DOS was therefore created only when the moon project failed. Chelomei was forced to work on DOS, and it severely impacted Almaz schedules. The Salyut name was later applied to both the DOS and Almaz stations, creating the impression in the outside world that they were built by one designer.
15 L1's were completed, of which only five ever returned to earth. With this successful final recovery, the programme is cancelled. The main cause of the project's failure was the unreliability of the UR-500K rocket.
After Mishin pushed his Indian Ocean recovery plan for the L3, the VVS insisted on sea trials of the capsule. These showed the cosmonauts had to get out within 30 to 35 minutes before the valves to the interior started leaking seawater. The L3 is also unsafe due to the EVA method of transfer to the LK of a single unassisted cosmonaut. The Krechet spacesuit is very bulky and unmanoeuvrable.
Prague wanted Gagarin's widow for International Women's Day.since Tereshkkova couldn't go, but she wants no part of public appearances.
After the crew has left the station, taken their seats in the capsule, and closed the hatch between the Soyuz BO orbital module and SA re-entry capsule, the strained voice of Volkov comes from space: 'Hatch not hermetically sealed? What's happening? What's going on?'. All this response to the fact that the caution and warning panel 'Hatch open' light has not gone out. Yeliseyev calmly advises the crew, 'Don't panic. Open the hatch, and move the wheel to the left to open. Close the hatch, and then move the wheel to the right six turns with full force'. The crew does this several times, but the light still won't go out. On a final attempt, with 6.5 turns of the wheel, the light goes out. On the second half of he 15th orbit, the crew lowers the pressure in the BO to 160 mm, and the hatch proves to be air-tight.
On the 16th orbit the crew separates their Soyuz from the Salyut station. At 21:35 they report normal separation and that they 'can see how the station moves away from the spacecraft'. They have enough propellant to stop the separation velocity, and take photographs of the station from 10 to 15 m away. They then back away to 30-40 m, and Patsayev takes another set of photographs documenting the condition of the station.
All else seemed ready to go. The estimated engine reliability was 93%. The turbogenerators had achieved 100% reliability in test stands. There were still dissenting voices on the use of LH2 - the final vote was 7 for flying with it, and 2 against.