|
Mercury
|
Program: Mercury. Objective: Manned. Type: Spacecraft. Mercury was America's first man-in-space project. Setting the precedent for the later Gemini, Apollo, and Shuttle programs, any capsule configuration proposed by the contractors was acceptable as long as it was the one NASA's Langley facility, and in particular, Max Faget, had developed. McDonnell, at that time a renegade contractor of innovative Navy fighters that had a history of problems in service, received the contract. The capsule had to be as small as possible to match the payload capability of America's first ICBM, the Atlas, which would be used for orbital missions. The resulting design was less than a third of the weight of the Russian Vostok spacecraft, and more limited as a result. While the Vostok was capable of missions of up to a week, the Mercury's final 24 hour mission was barely completed, with virtually all of the spacecraft's systems having broken down by the end. NASA felt lucky to have astronaut Cooper back alive (although the flight demonstrated a pinpoint re-entry was possible with no electrical power, no ECS, no guidance or instruments!) and cancelled Alan Shepard's desired week-long Mercury 10 flight. Major Events:
- 1958 January 29-31 - Conference reviews concepts for manned orbital vehicles.. Spacecraft: Mercury, Project 7969.
A conference was held at Wright-Patterson Air Force Base, Ohio, to review concepts for manned orbital vehicles. The NACA informally presented two concepts then under study at Langley Aeronautical Laboratory: the one proposed by Maxime A. Faget involved a ballistic, high-drag capsule with heat shield on which the pilot lies prone during reentry, with reentry being accomplished by reverse thrust at the apogee of the elliptical orbit involving a deceleration load of about 8g, and proceeding to impact by a parachute landing; the other Langley proposal called for the development of a triangular planform vehicle with a flat bottom having some lift during reentry. At this same meeting there were several Air Force contractor presentations. These were as follows: Northrop, boost-glide buildup to orbital speed; Martin, zero-lift vehicle launched by a Titan with controlled flight estimated to be possible by mid-1961; McDonnell, ballistic vehicle resembling Faget's proposal, weighing 2,400 pounds and launched by an Atlas with a Polaris second stage; Lockheed, a 20 degree semiapex angle cone with a hemispherical tip of 1-foot radius, pilot in sitting position facing rearward, to be launched by an Atlas-Hustler combination; Convair reviewed a previous proposal for a large-scale manned space station, but stated a minimum vehicle - a 1,000-pound sphere - could be launched by an Atlas within a year; Aeronutronics, cone-shaped vehicle with spherical tip of 1-foot radius, with man enclosed in sphere inside vehicle and rotated to line the pilot up with accelerations, and launched by one of several two-stage vehicles; Republic, the Ferri sled vehicle, a 4,000 pound, triangular plan with a two-foot diameter tube running continuous around the leading and trailing edge and serving as a fuel tank for final-stage, solid-propellant rockets located in each wing tip, with a man in small compartment on top side, and with a heat-transfer ring in the front of the nose for a glide reentry of 3,600 miles per hour with pilot ejecting from capsule and parachuting down, and the launch vehicle comprising three stages (also see July 31, 1958 entry); AVCO, a 1,500-pound vehicle sphere launched by a Titan, equipped with a stainless-steel-cloth parachute whose diameter would be controlled by compessed air bellows and which would orient the vehicle in orbit, provide deceleration for reentry, and control drag during reentry; Bell, reviewed proposals for boost-glide vehicles, but considered briefly a minimum vehicle, spherical in shape, weighing about 3,000 pounds; Goodyear, a spherical vehicle with a rearward facing tail cone and ablative surface, with flaps deflected from the cone during reentry for increased drag and control, and launched by an Atlas or a Titan plus a Vanguard second stage; North American, extend the X-15 program by using the X-15 with a three-stage launch vehicle to achieve a single orbit with an apogee of 400,000 feet and a perigee of 250,000, range about 500 to 600 miles and landing in the Gulf of Mexico, and the pilot ejecting and landing by parachute with the aircraft being lost.
- 1958 January 31 - USAF proposes NACA participation in the Air Force effort in the manned ballistic rocket program.. Spacecraft: Mercury, Project 7969.
Lieutenant General Donald Putt, Air Force Director of Research and Development, sent a letter to Dr. Hugh Dryden, Director of NACA, inviting NACA participation in the Air Force effort in the manned ballistic rocket program. Dr. Dryden informed the Air Force that NACA was preparing manned spacecraft designs for submission in March 1958.
- 1958 March 10 - MISS Working Conference. Spacecraft: Mercury, Project 7969.
A working conference in support of the Air Force 'Man-in-Space Soonest' (MISS) was held at the Air Force Ballistic Missile Division in Los Angeles, California. General Bernard Schriever, opening the conference, stated that events were moving faster than expected. By this statement he meant that Roy Johnson, the new head of the Advanced Research Projects Agency, had asked the Air Force to report to him on its approach to putting a man in space soonest. Johnson indicated that the Air Force would be assigned the task, and the purpose of the conference was to produce a rough-draft proposal. At that time the Air Force concept consisted of three stages: a high-drag, no-lift, blunt-shaped spacecraft to get man in space soonest, with landing to be accomplished by a parachute; a more sophisticated approach by possibly employing a lifting vehicle or one with a modified drag; and a long-range program that might end in a space station or a trip to the moon.
- 1958 March 12 - The NACA staff completed a program outline for conducting the manned satellite program.. Spacecraft: Mercury.
At that time, NACA was already actively engaged in research and study of several phases. For example, in the basic studies category effort had been expended on the study of orbits and orbit control, space physical characteristics, configuration studies, propulsion system research, human factors, structures and materials, satellite instrumentation, range requirements, and noise and vibration during reentry and exit. In addition, NACA outlined the complete program covering full-scale studies of mockups, simulators, and detail designs; full-scale vertical and orbiting flights involving unmanned, animal, and manned flights and recovery; and exploitation of the program to increase the payloads. As to the design concepts for such a program, NACA believed that the Atlas launch vehicle was adequate to meet launch-vehicle requirements for manned orbital flights; that retrograde and vernier controllable thrust could be used for orbital control; that heat-sink or lighter material could be used against reentry heating; that guidance should be ground programed with provisions for the pilot to make final adjustments; that recovery should be accomplished at sea with parachutes used for letdown; that a network of radar stations should be established to furnish continuous tracking; and that launchings be made from Cape Canaveral. It was estimated that with a simple ballistic shape accelerations would be within tolerable limits for the pilot. Temperature control, oxygen supply, noise, and vibration were considered engineering development problems, which could be solved without any special breakthroughs.
- 1958 June 5 - Advanced Research Projects Agency manned space project.. Spacecraft: Mercury.
After serving as a liaison officer of NACA and as a participating member of an Advanced Research Projects Agency panel, Maxime A. Faget reported to Dr. Hugh Dryden on resulting studies and attending recommendations on the subject of manned space flight. He stated that the Advanced Research Projects Agency panel was quite aware that the responsibility for such a program might be placed with the soon-to-be-created civilian space agency, although they recommended program management be placed with the Air Force under executive control of NACA and the Advanced Research Projects Agency. The panel also recommended that the program start immediately even though the specific manager was, as yet, unassigned. Several of the proposals put forth by the panel on the proposed development were rather similar to the subsequent evolvement. The system suggested by the Advanced Research Projects Agency was to be based on the use of the Atlas launch vehicle with the Atlas-Sentry system serving as backup; retrorockets were to be used to initiate the return from orbit; the spacecraft was to be nonlifting, ballistic type, and the crew was to be selected from qualified volunteers in the Army, Navy, and Air Force.
- 1958 July 16 - Congress passed the National Aeronautics and Space Act of 1958..
- 1958 August - Eisenhower assigns the manned space flight program to NASA.. Spacecraft: Mercury, Project 7969.
President Eisenhower assigned the responsibility for the development and execution of a manned space flight program to the National Aeronautics and Space Administration. However, NASA did not become operational until October 1, 1958.
- 1958 September 24-October 1 - Basic plan for a manned satellite program..
A series of meetings were held in Washington, with Robert R. Gilruth serving as chairman to draft a manned satellite program and provide a basic plan for meeting the objectives of this program. Others attending included S. B. Batdorf, A. J. Eggers, Maxime A. Faget, George Low, Warren North, Walter C. Williams, and Robert C. Youngquist.
- 1958 October 1 - NASA created.
NASA was activated in accordance with the terms of Public Law 85-568, and the nonmilitary space projects which had been conducted by the Advanced Research Projects Agency were transferred to the jurisdiction of the NASA. Concurrently, NACA, after a 43-year tenure, was inactivated, and its facilities and personnel became a part of NASA.
- 1958 October 3-7 - Plans of the Mercury manned satellite project presented to Advanced Research Projects Agency.. Spacecraft: Mercury.
Studies and plans of the manned satellite project were presented to Advanced Research Projects Agency on October 3 and to Dr. T. Keith Glennan, NASA Administrator, on October 7. On October 7, 1958, Dr. Glennan approved the project by saying, in effect, 'Let's get on with it.'
- 1958 October 7 - Project Mercury organized.. Spacecraft: Mercury.
NASA formally organized Project Mercury to: (1) place manned space capsule in orbital flight around the earth; (2) investigate man's reactions to and capabilities in this environment; and (3) recover capsule and pilot safely. A NASA Space Task Group organized at Langley Research Center drew up specifications for the Mercury capsule, based on studies by the National Advisory Committee for Aeronautics during the preceding 12 months, and on discussions with the Air Force which had been conducting related studies.
- 1958 October 17-18 - Negotiations for Mercury Atlas launch vehicles. Launch Vehicle: Atlas D.
Langley Research Center personnel visited the Air Force Ballistic Missile Division, Inglewood, California, to open negotiations for procuring Atlas launch vehicles for the manned satellite project.
- 1958 October 21 - Bidders' briefing for the Mercury Little Joe launch vehicle.. Launch Vehicle: Little Joe.
A bidders' briefing for the Little Joe launch vehicle was held. As earlier mentioned, this launch vehicle was to be used in the development phase of the manned satellite project. The Little Joe launch vehicle was 48 feet in height, weighed (at maximum) 41,330 pounds, was 6.66 feet in diameter, consisted of four Pollux and four Recruit clustered, solid-fuel rockets, could develop a thrust of 250,000 pounds, and could lift a maximum payload of 3,942 pounds.
- 1958 November - Mercury scale model transonic tests.. Spacecraft: Mercury.
A scale model of the Mercury spacecraft (without escape tower), oriented for the reentry phase, was tested at transonic Mach numbers in a 1-foot transonic test tunnel at the Arnold Engineering Development Center, Tullahoma, Tennessee.
- 1958 November 7 - Contractor briefing on the Mercury manned spacecraft. Spacecraft: Mercury.
A contractor briefing, attended by some 40 prospective bidders on the manned spacecraft, was held at the Langley Research Center. More detailed specifications were then prepared and distributed to about 20 manufacturers who had stated an intention to bid on the project.
- 1958 November 14 - Specifications for Mercury issued.. Spacecraft: Mercury.
Specifications for the manned spacecraft (Specification Number S-6) were issued, and final copies were mailed on November 17, 1958, to 20 firms which had indicated a desire to be considered as bidders.
- 1958 November 24 - Space Task Group orders first Mercury Atlas missile.. Launch Vehicle: Atlas D.
The Space Task Group placed an order for one Atlas launch vehicle with the Air Force Missile Division, Inglewood, California, as part of a preliminary research program leading to manned space flight. The National Aeronautics and Space Administration Headquarters requested that the Air Force construct and launch one Atlas C launch vehicle to check the aerodynamics of the spacecraft. It was the intention to launch this missile about May 1959 in a ballistic trajectory. This was to be the launch vehicle for the Big Joe reentry test shot, but plans were later changed and an Atlas Model D launch vehicle was used instead.
- 1958 December 1 - Design of the Mercury Big Joe spacecraft completed..
Design of the Big Joe spacecraft for the Project Mercury reentry test (the spacecraft would be boosted by an Atlas launch vehicle over a ballistic trajectory) was accomplished by the Space Task Group. Construction of the spacecraft was assigned as a joint task of the Langley and Lewis Research Centers under the direction of the Space Task Group. The instrument package was developed by Lewis personnel assigned to the Space Task Group, and these individuals later became the nucleus of the Space Task Group's Flight Operations Division at Cape Canaveral.
- 1958 December 2 - Redstone and Jupiter launch vehicle use on Mercury discussed.. Launch Vehicle: Redstone, Jupiter.
Space Task Group officials visited the Army Ballistic Missile Agency to determine the feasibility of using the Jupiter launch vehicle for the intermediate phase of Project Mercury, to discuss the Redstone program, and to discuss the cost for Redstone and Jupiter launch vehicles.
- 1958 December 9 - Mercury astronaut selection procedure..
An aeromedical selection team composed of Major Stanley C. White, Air Force; Lt. Robert B. Voas, Navy; and Captain William Augerson, Army, drafted a tentative astronaut selection procedure. According to the plan, representatives from the services and industry would nominate 150 men by January 21, 1959; 36 of these would be selected for further testing which would reduce the group to 12; and in a 9-month training period, a hard core of 6 men would remain. At the end of December 1958, this plan was rejected.
- 1958 December 11 - Eleven firms submitted proposals for the development of Mercury manned spacecraft.. Spacecraft: Mercury.
These were AVCO, Chance-Vought, Convair, Douglas, Grumman, Lockheed, Martin, McDonnell, North American, Northrop, and Republic. In addition, Winzen Research Laboratories submitted an incomplete proposal.
- 1958 December 31 - Letter-of-intent placed for Mercury Little Joe Test air frames.. Launch Vehicle: Little Joe.
The letter-of-intent was placed with North American Aviation for the fabrication of the Little Joe Test vehicle air frame. Delivery of the air frames for flight testing was scheduled to occur every three weeks beginning in June 1959. Space Task Group had ordered all the major rocket motors, which were scheduled for delivery well ahead of the Little Joe flight test schedule. The spacecraft for this phase of the program was being designed and construction would start shortly. Thus the Little Joe program should meet its intended flight test schedule.
- 1959 January - Balloon flights planned for Mercury.. Spacecraft: Mercury.
Balloon flights were planned for high-altitude qualification tests of the complete spacecraft, including all instrumentation, retrorockets, drogue parachute system, and recovery. Later balloon flights would be manned to provide as much as 24 hours of training followed by recovery at sea. The Space Task Group made surveys of organizations experienced in the balloon field and recommended that the Air Force Cambridge Research Center be given responsibilities for designing, contracting, and conducting the balloon program.
- 1959 January - Development of the Mercury pressure suit was started.. Spacecraft: Mercury Space Suit.
- 1959 January - Honeywell named subcontractor for the Mercury stabilization system.. Spacecraft: Mercury.
McDonnell, as prime contractor, selected Minneapolis-Honeywell as subcontractor for the Mercury stabilization system. At that time, other subcontractors were under consideration for the fabrication of various components: Bell Aircraft Rockets Division, reaction control system; and General Electric, Barnes Instruments, and Detroit Controls were being considered for fabrication of the horizon scanner. Later Bell and Barnes were awarded contracts for respective components.
- 1959 January-February - Study contracts for tracking instrumentation for Project Mercury..
Study contracts were awarded to Aeronutronics, Space Electronics, and the Massachusetts Institute of Technology Lincoln Laboratory for assistance in developing plans for tracking and ground instrumentation for Project Mercury.
- 1959 January 5 - Mercury pilot selection qualifications.
Qualifications were established for pilot selection in a meeting at the NASA Headquarters. These qualifications were as follows: age, less than 40; height, less than 5 feet 11 inches; excellent physical condition; bachelor's degree or equivalent; graduate of test pilot school; 1,500 hours flight time; and a qualified jet pilot.
- 1959 January 9 - McDonnell selected to produce the Mercury spacecraft.. Spacecraft: Mercury.
The Source Selection Board at NASA Headquarters composed of Abe Silverstein, Ralph Cushman, George Low, Walter Schier, DeMarquis Wyatt, and Charles Zimmerman, completed their findings and reported to Dr. T. Keith Glennan, the Administrator. McDonnell Aircraft Corporation was selected as the prime contractor to develop and produce the Mercury spacecraft.
- 1959 January 16 - Eight Redstone and two Jupiter launch vehicles for Mercury. Launch Vehicle: Redstone, Jupiter.
NASA requested the Army Ordnance Missile Command, Huntsville, Alabama, to construct and launch eight Redstone launch vehicles and two Jupiter launch vehicles in support of Project Mercury manned and unmanned flights.
- 1959 January 21 - The screening of records for prospective Mercury astronauts began..
- 1959 February 1-14 - 110 US military pilots appeared to qualify for Mercury.
Some 508 records were reviewed for prospective pilot candidates of which about 110 appeared to qualify. The special committee on Life Sciences decided to divide these into two groups and 69 prospective pilot candidates were briefed and interviewed in Washington. Out of this number, 53 volunteered for the Mercury program, and 32 of the 53 were selected for further testing. The committee agreed there was no further need to brief other individuals, because of the high qualities exhibited in the existing pool of candidates. These 32 were scheduled for physical examination at the Lovelace Clinic, Albuquerque, New Mexico.
- 1959 February - NASA/USAF responsibilities for the first two Mercury Atlas firings.. Launch Vehicle: Atlas D.
During a meeting between personnel of the Space Task Group and the Air Force Ballistic Missile Division, the responsibilities of the two organizations were outlined for the first two Atlas firings. Space Technology Laboratories, under Air Force Ballistic Missile Division direction, would select the design trajectories according to the specifications set forth by the Space Task Group. These specifications were to match a point in the trajectory at about 450,000 feet, corresponding to a normal reentry condition for the manned spacecraft after firing of the retrorockets at an altitude of 120 nautical miles. Space Technology Laboratories would also provide impact dispersion data, data for range safety purposes, and the necessary reprograming of the guidance computers. The spacecraft for the suborbital Atlas flights would be manufactured under the deriction of the Lewis Research Center, based on Space Task Group designs. Space Task Group was developing the spacecraft instrumentation, with a contingent of personnel at the Lewis Research Center. The attitude control system was being developed by Lewis.
- 1959 February 6 - Formal contract for 12 Mercury spacecraft with McDonnell.. Spacecraft: Mercury.
Following industry-wide competition, a formal contract for research and development of the Mercury spacecraft was negotiated with the McDonnell Aircraft Corporation. The contract called for design and construction of 12 Mercury spacecraft, but it did not include details on changes and ground support equipment which were to be negotiated as the project developed. Later, orders were placed with the company for eight additional spacecraft, two procedural trainers, an environmental trainer, and seven checkout trainers. McDonnell had been engaged in studying the development of a manned spacecraft since the NACA presentation in mid-March of 1958.
- 1959 February 7 - Medical tests for the Mercury astronaut selection started..
At the Lovelace Clinic, Albuquerque, New Mexico, the medical tests for the Mercury astronaut selection were started.
- 1959 February 10 - Wiind tunnel tests of Project Mercury configuration models were started.. Spacecraft: Mercury.
By the end of the year, over 70 different models had been tested by facilities at the Air Force's Arnold Engineering Development Center and the NASA Langley, Ames, and Lewis Research Centers.
- 1959 February 12-13 - Atlas launch vehicles in Project Mercury.. Launch Vehicle: Atlas D.
Discussions were held at Langley Field between the Space Task Group and the Air Force Ballistic Missile Division covering aspects of the use of Atlas launch vehicles in Project Mercury. Specifically discussed were technical details of the first Atlas test flight (Big Joe), the abort sensing capability for later flights, and overall program objectives.
- 1959 March 8 - Mercury abort test conducted at Wallops Island. Spacecraft: Mercury.
An abort test was conducted at Wallops Island on a full-scale model of the spacecraft with the escape tower, using a Recruit escape rocket. The configuration did not perform as expected (erratic motion), and as a result, the Langley Research Center was requested to test small-scale flight models of the abort system to determine its motion in flight.
- 1959 March 11 - First full-scale test simulating a Mercury pad-abort situation.. Spacecraft: Mercury.
Langley's Pilotless Aircraft Research Division conducted, at Wallops Island, the first full-scale test simulating a pad-abort situation. A full weight and size spacecraft was used. For the first 50 feet the flight was essentially straight, indicating the successful functioning of the abort rocket. Thereafter, the spacecraft pitched through several turns and impacted a short distance from the shore. The malfunction was traced to the loss of a graphite insert from one of the three abort rocket nozzles, which caused a misalignment of thrust.
- 1959 March 17-18 - Mercury mock-up inspection.. Spacecraft: Mercury.
A Mock-Up Inspection Board meeting was held at the McDonnell plant to review the completed spacecraft mock-up. As a result of this meeting, the contractor was directed to restudy provisions made for pilot egress; rearrange crew space to make handles, actuators, and other instruments more accessible to the pilot; and modify the clock, sequence lights, and other displays. This same type of meeting was held on many subsequent occasions to review production spacecraft.
- 1959 March 23 - DX priority procurement rating in support of Project Mercury.. Spacecraft: Mercury.
As of this date, the McDonnell Aircraft Corporation listed some 32 items that required a DX priority procurement rating in support of Project Mercury. This highest national priority procurement rating had been requested by NASA on November 14, 1958.
- 1959 March 26 - Hypersonic flight tests for the Mercury spacecraft.. Spacecraft: Mercury.
The Langley Research Center received approval for funds to conduct hypersonic flight tests for the Mercury spacecraft. Langley's Pilotless Aircraft Research Division would conduct tests on heat transfer rates at a velocity of mach 17, and dynamic behavior tests from a velocity of mach 10 to a subsonic speed.
- 1959 April - Mercury parachute design unsafe for operation.. Spacecraft: Mercury.
In the recovery landing system, the extended-skirt main parachute was found to be unsafe for operation at altitudes of 10,000 feet and was replaced by a 'ring-sail' parachute of similar size. This decision was made after a drop when the main parachute failed to open and assumed a 'squidding' condition. Although little damage was sustained by the spacecraft on water impact, parachute experts decided that the ring-sail configuration should be adopted, and the air drop spacecraft were fitted.
- 1959 April 2 - Seven astronauts selected for Mercury project.. Spacecraft: Mercury.
Seven astronauts were selected for Project Mercury after a series of the most rigorous physical and mental tests ever given to U.S. test pilots. Chosen from a field of 110 candidates, the finalists were all qualified test pilots: Capts. Leroy G. Cooper, Jr., Virgil I. Grissom, and Donald K. Slayton, (USAF); Lt. Malcolm S. Carpenter, Lt. Comdr. Alan B. Shepard, Jr., and Lt. Comdr. Watler M. Schirra, Jr. (USN); and Lt. Col. John H. Glenn (USMC).
- 1959 April 2-16 - Project Mercury animal payload program.. Spacecraft: Mercury. Launch Vehicle: Little Joe.
NASA and the military services conducted meetings to draft final plans for the Project Mercury animal payload program. The animal program was planned to cover nine flights, involving Little Joe, Redstone, Jupiter, and Atlas launch vehicles.
- 1959 April 2 - Bidders briefing for Project Mercury worldwide tracking range.
A preliminary briefing was conducted for prospective bidders on construction of the worldwide tracking range for Project Mercury. This meeting was attended by representatives from 20 companies. At this time the preliminary plan called for an orbital mission tracking network of 14 sites. Contacts had not been made with the governments of any of the proposed locations with the exception of Bermuda. It was planned that all the sites would have facilities for telemetry, voice communications with the pilot, and teletype (wire or radio) communications with centers in the United States for primary tracking. The tracking sites would provide the control center at Cape Canaveral, Florida, with trajectory predictions; landing-area predictions; and vehicle, systems, and pilot conditions.
- 1959 April 9-10 - Escape configurations for Mercury spacecraft. Spacecraft: Mercury.
Investigations of two escape configurations for Mercury spacecraft were conducted in a 16-foot transonic circuit at the Arnold Engineering Development Center, Tullahoma, Tennessee, for determination of static stability and drag characteristics of the configurations.
- 1959 April 12 - Mercury impact tests. Spacecraft: Mercury.
Tests were in progress at Langley in which an aluminium honeycomb structure was used partially to absorb the spacecraft impact load. Robert R. Gilruth, Project Mercury Director, had stated his belief of this requirement on January 16, 1959.
- 1959 April 12 - Space Task Group conducted the second full-scale Mercury beach abort test on Wallops Island.. Spacecraft: Mercury.
A deliberate thrust misalignment of 1 inch was programed into the escape combination. Lift-off was effected cleanly, and a slow pitch started during the burning of the escape rocket motor. The tower separated as scheduled and the drogue and main parachutes deployed as planned. The test was fully successful.
- 1959 April 13 - Mercury small-scale escape-tower combinations launched. Spacecraft: Mercury.
Two small-scale spacecraft escape-tower combinations were launched successfully at Wallops Island. On the next day a full-scale spacecraft escape system was launched. The complete sequence of events - escape system firing, escape tower jettisoning, parachute deployment, landing, and helicopter recovery - was satisfactory.
- 1959 April 22 - Tower configuration best escape system for the Mercury spacecraft.. Spacecraft: Mercury.
In a meeting at Langley, NASA officials concluded that the tower configuration was the best escape system for the Mercury spacecraft and development would proceed using this concept. However, limited studies of alternate configurations would continue.
- 1959 April 27 - Project Mercury was accorded the DX priority procurement rating.. Spacecraft: Mercury.
- 1959 April 27 - Project Mercury astronauts reported for duty.
The seven Project Mercury astronauts reported for duty. A tentative schedule of Mercury astronaut activities for the first months of training was issued. Actual training began the next day. Within 3 months the astronauts were acquainted with the various facets of the Mercury program. The first training week was as follows: Monday, April 27, check in; April 28, general briefing; April 29, spacecraft configuration and escape methods; April 30, support and restraint; May 1, operational concepts and procedures. These lectures were presented by specialists in the particular field of study. Besides the above, unscheduled activities involved 3 hours flying time and 4 hours of athletics.
- 1959 April 27 - Mercury search and rescue procedures developed.. Spacecraft: Mercury.
Meeting of DOD working group on Project Mercury search and recovery operations was held at Patrick Air Force Base, with major emphasis placed on the first two ballistic Atlas shots, and command relationships.
- 1959 May 6 - Pigs not to fly in space in Project Mercury. Spacecraft: Mercury. Launch Vehicle: Little Joe.
Pigs were eliminated as Little Joe flight test subjects when studies disclosed that they could not survive long periods of time on their backs. However, McDonnell did use a pig, 'Gentle Bess,' to test the impact crushable support, and the test was successful.
- 1959 May 21 - Specifications for Tracking and Ground Instrumentation System for Project Mercury.
Langley Specification Number S-45, entitled 'Specifications for Tracking and Ground Instrumentation System for Project Mercury,' was issued. Proposals were received from seven contractor teams by June 22, 1959, and technical evaluations were started.
- 1959 May 22 - The Project Mercury balloon flight test program was canceled.. Spacecraft: Mercury.
The Space Task Group oficials determined that the spacecraft could be tested environmentally in the Lewis Research Center's altitude wind tunnel. This included correct temperature and altitude simulations to 80,000 feet. The pilot could exercise the attitude control system and retrorockets could be fired in the tunnel. Because an active contract did exist with the Air Force, it was decided the two balloon drop tests with unmanned boiler-plate spacecraft would be accomplished.
- 1959 May 28 - First two Mercury Little Joe booster airframes delivered. Launch Vehicle: Little Joe.
North American Aviation delivered the first two Little Joe booster airframes, and noted that the four remaining were on fabrication schedule. The planned program was moving smoothly, for rocket motors to be used in the first flight were available at Wallops Station, Virginia, the test flight launching site. In addition, procurement of the test spacecraft incorporating Mercury flight items was on schedule, and the first spacecraft had been instrumented by Space Task Group personnel. Work was also in progress on other test spacecraft.
- 1959 June - Northrop to fabricate the landing system for Mercury.. Spacecraft: Mercury.
McDonnell selected Northrop as the subcontractor to design and fabricate the landing system for Project Mercury. Northrop technology for landing and recovery systems dated back to 1943 when that company developed the first parachute recovery system for pilotless aircraft. For Project Mercury, Northrop developed the 63-foot ring-sail main parachute.
- 1959 June 5 - Flight instrumentation necessary to support the Mercury-Atlas program.. Launch Vehicle: Atlas D.
Space Technology Laboratories and Convair completed an analysis of flight instrumentation necessary to support the Mercury-Atlas program. The primary objective of the study was to select a light-weight telemetry system. A system weighing 270 pounds was recommended, and the National Aeronautics and Space Administration concurred with the proposal.
- 1959 June 8 - Mercury Big Joe spacecraft for the reentry test was delivered to Cape Canaveral..
- 1959 June 14-27 - Mercury spacecraft being designed to withstand 149 decibels.. Spacecraft: Mercury.
A visit was made to McDonnell and it was learned that the Mercury spacecraft was being designed structurally to withstand 149 decibels overall noise level. McDonnell, however, anticipated that the actual maximum level would not be above 128 decibels. Space Task Group personnel felt that even the 128 decibels were too high for pilot comfort, and extensive research toward the resolution of this matter was started.
- 1959 June 18 - Centrifuge program to investigate the role of a pilot in the launch of a multi-stage vehicle..
A centrifuge program was conducted at Johnsville, Pennsylvania, to investigate the role of a pilot in the launch of a multi-stage vehicle. Test subjects were required to perform boost-control tasks, while being subjected to the proper boost-control accelerations. The highest g-force experienced was 15, and none of the test subjects felt they reached the limit of their control capability. As a note of interest, one of the test subjects, Neil Armstrong, was later selected for the Gemini program in September 1962.
- 1959 June 25 - Mercury recovery airdrop test.. Spacecraft: Mercury.
Navy surface vessels and aircraft were used in a recovery operation after an airdrop of a spacecraft off the coast from Jacksonville, Florida. The spacecraft was purposely dropped 40 miles away from the predicted impact point and 45 miles away from the nearest ship. Recovery was effected in 2 and one half hours.
- 1959 June 28 - Ablation materials for the Mercury Little Joe flights.. Spacecraft: Mercury. Launch Vehicle: Little Joe.
Between June 28 and July 11, 1959, 12 heat-transfer tests were made in the Preflight Jet Test facility at Wallops Island on several ablation materials being considered for use on the spacecraft afterbody (not heat shield) for the Little Joe flights. Test conditions simulated those of actual Little Joe trajectories. Of the materials used, triester polymer and thermolag demonstrated the capability to protect the spacecraft against expected heat loads.
- 1959 July 1-2 - Mercury pressure suit compatibility evaluation.. Spacecraft: Mercury Space Suit.
A pressure suit compatibility evaluation in the Mercury spacecraft mock-up was performed in suits submitted by the David Clark Company, B. F. Goodrich Company, and International Latex Company. Four subjects participated in the tests.
- 1959 July 12 - Instrumentation to measure noise level during the Mercury Big Joe-Atlas launching.. Launch Vehicle: Atlas D.
An agreement was made with the Air Force for Space Task Group to place microphone pickups on the skin of the Atlas launch vehicle as a part of the instrumentation to measure noise level during the Big Joe-Atlas launching. Distribution of the microphones was as follows: one inside the Mercury spacecraft, three externally about midway of the launch vehicle, and one on the Atlas skirt.
- 1959 July 20 - Western Electric Company selected for the Mercury tracking network..
Negotiations for construction of the Mercury tracking network were started with the Western Electric Company and their subcontractors (Bendix Aviation, International Business Machines, Bell Telephone Laboratories, and Burns and Roe), and a letter contract was signed on July 30, 1959, for the entire range. This included radar tracking; telemetry receiving, recording, and display; communications to both the spacecraft and surface stations; and the computing and control facilities.
- 1959 July 28 - Second beach abort test leading to the Mercury Little Joe test series.. Spacecraft: Mercury. Launch Vehicle: Little Joe.
A boilerplate spacecraft, instrumented to measure sound pressure level and vibration, was launched in the second beach abort test leading to the Little Joe test series. The purpose of the instrumentation was to obtain measurement of the vibration and sound environment encountered on the capsule during the firing of the Grand Central abort rocket. Memo, Charles A. Hardesty to NASA Langley IRD files, subject: Sound Measurements on the Second Beach Abort Test on the Little Joe Capsule, Oct. 9, 1959.
- 1959 August 21 - Mercury LJ-1. Spacecraft: Mercury. Launch Site: Wallops Island. Launch Vehicle: Little Joe.
During the countdown of the first programed Little Joe launching (LJ-1 beach abort test) at Wallops Island, the escape rocket fired prematurely 31 minutes before the scheduled launch. The spacecraft rose to an altitude of 2,000 feet and landed about 2,000 feet from the launch site. Premature firing was caused by a faulty escape circuit.
- 1959 September 10-11 - Mercury spacecraft mock-up review. Spacecraft: Mercury.
At a spacecraft mock-up review, the astronauts submitted several recommended changes. These involved a new instrument panel, a forward centerline window, and an explosive side egress hatch.
- 1959 September 21 - Effects of sustained acceleration on the pilot's ability to control a vehicle.. Spacecraft: Mercury.
Between September 21 and October 10, 1959, a research program was carried out by the Aviation Medical Acceleration Laboratory to measure the effects of sustained acceleration on the pilot's ability to control a vehicle. Various side-arm controllers were used, and it appeared that the three-axis type (yaw, roll, and pitch) was the most satisfactory. Later this configuration was extensively evaluated and adopted for use in the control system of the Mercury spacecraft.
- 1959 October - McDonnell received the first Mercury ablative heat shield. Spacecraft: Mercury.
McDonnell received the first ablative heat shield, designated for installation on Spacecraft No. 1. This particular heat shield was based on the Big Joe design, and was manufactured by General Electric.
- 1959 October 1 - Funds approved for major changes to the Mercury spacecraft. Spacecraft: Mercury.
Funds were approved by NASA Headquarters for the following major changes to the Mercury spacecraft: egress hatch installation (CCP-58-1), astronaut observation window installation (CCP-73); rate stabilization and control system (CCP-61-2), main instrument and panel redesign (CCP-76), installation of reefed ringsail landing parachute (CCP-41), and nonspecification configurations of spacecraft (CCP-8). With reference to the last item, the original contract with McDonnell had specified only one spacecraft configuration, but the various research and development flight tests required changes in the configuration.
- 1959 October 13 - Explorer VII.
Explorer VII achieved orbit and began providing significant geophysical information on solar and earth radiation, magnetic storms, and micrometeorite penetration. This satellite also successfully demonstrated a method of controlling internal temperatures.
- 1959 November - Mercury full-pressure suits delivered.. Spacecraft: Mercury Space Suit.
Between November 1959 and January 1960, 10 developmental Mercury full-pressure suits were delivered. These suits were used in various Mercury training and development programs. Several problem areas were denoted. One involved stretching which complicated the suit mobility problem. This matter was being investigated, and one of the solutions was felt to be undersizing to allow for a suit growth factor. In addition, modifications would have to be made in suit insulation to provide for better pilot mobility. These problems were to be expected in a developmental program.
- 1959 November - Mercury first manned development system tests. Spacecraft: Mercury, Mercury Space Suit.
The first manned development system tests were completed at the AiResearch Manufacturing Division, Garrett Corporation. Tests were conducted in the altitude chamber to determine proper functioning of all system valves and components. A McDonnell subject was clothed in a Mercury-type presure suit for these tests. Preliminary data from these tests indicated that the system functioned satisfactorily.
- 1959 November 4 - Mercury LJ-1A. Spacecraft: Mercury. Launch Site: Wallops Island. Launch Vehicle: Little Joe.
Little Joe 1-A (LJ-1A) was launched in a test for a planned abort under high aerodynamic load conditions. This flight was a repeat of the Little Joe (LJ-1) that had been planned for August 21, 1959 (escape rocket fired 31 min before the intended launch of the Little Joe launch vehicle). After lift-off, the pressure sensing system was to supply a signal when the intended abort dynamic pressure was reached (about 30 sec after launch). An electrical impulse was then sent to the explosive bolts to separate the spacecraft from the launch vehicle. Up to this point, the operation went as planned, but the impulse was also designed to start the igniter in the escape motor. The igniter activated, but pressure failed to build up in the motor until a number of seconds had elapsed. Thus the abort maneuver, the prime mission of the flight, was accomplished at a dynamic pressure that was too low. For this reason a repeat of the test was planned. All other events from the launch through recovery occurred without incident. The flight attained an altitude of 9 statute miles, a range of 11.5 statute miles, and a speed of 2,021.6 miles per hour.
- 1959 November 8 - Design of the Mercury Control Center was completed.. Spacecraft: Mercury.
Between this date and December 5, 1959, the tentative design and layout of the Mercury Control Center to be used to monitor the orbiting flight of the Mercury spacecraft were completed. The control center would have trend charts to indicate the astronaut's condition and world map displays to keep continuous track of the Mercury spacecraft.
- 1959 December - Mercury astronaut F-100 weightless flying training program.
A weightless flying training program was started by the Mercury astronauts in the F-100 aircraft at Edwards Air Force Base, California. Eating, drinking, and psychomotor tests were conducted while the astronauts were in a weightless state.
- 1959 December 4 - Mercury Little Joe 2 (LJ-2). Spacecraft: Mercury. Launch Site: Wallops Island.
LJ-2 was launched from Wallops Island to determine the motions of the spacecraft escape tower combination during a high-altitude abort, entry dynamics without a control system, physiological effects of acceleration on a small primate, operation of the drogue parachute, and effectiveness of the recovery operation. Telemetry was set up to record some 80 bits of information on the flight. The abort sequence was initiated by timers after 59 seconds of elapsed flight time at an altitude of about 96,000 feet and a speed of Mach 5.5. Escape motor firing occurred as planned and the spacecraft was whisked away at a speed of about Mach 6 to an apogee of 53.03 statute miles. All other sequences operated as planned, and spacecraft recovery was effected in about 2 hours from lift-off. The primate passenger, 'Sam,' an American-born rhesus monkey, withstood the trip and the recovery in good condition. All objectives of the mission were met.
- 1960 January 18 - Mercury-Atlas flight test working group to become a standing coordination body.. Launch Vehicle: Atlas D.
A proposal was made by Walter C. Williams, Associate Director of Project Mercury Operations, that the Mercury-Atlas flight test working group become an official and standing coordination body. This group brought together representation from the Space Task Group, Air Force Ballistic Missile Division, Convair Astronautics, McDonnell Aircraft Corporation, and the Atlantic Missile Range. Personnel from these organizations had met informally in the past on several occasions.
- 1960 January 21 - Mercury LJ-1B. Spacecraft: Mercury. Launch Site: Wallops Island. Launch Vehicle: Little Joe.
Little Joe 1-B (LJ-1B) was launched from Wallops Island with a rhesus monkey, 'Miss Sam,' aboard. Test objectives for this flight were the same as those for Little Joe 1 (LJ-1) in which the escape tower launched 31 minutes before the planned launch, and Little Joe 1-A (LJ-1A), wherein the dynamic buildup in the abort maneuver was too low. A physiological study of the primate, particularly in areas applying to the effects of the rapid onset of reverse acceleration during abort at maximum dynamic pressure, was also made. In addition, the Mercury helicopter recovery system was exercised. During the mission, all sequences operated as planned; the spacecraft attained a peak altitude of 9.3 statute miles, a range of 11.7 statute miles, and a maximum speed of 2,021.6 miles per hour. Thirty minutes from launch time, a Marine recovery helicopter deposited the spacecraft and its occupant at Wallops Station. 'Miss Sam' was in good condition, and all test objectives were successfully fulfilled.
- 1960 February - Mercury astronauts instruction in celestial navigation.
As part of their training program, the astronauts received 2 days of instruction in star recognition and celestial navigation presented by Dr. James Balten at the Morehead Planetarium in Chapel Hill, North Carolina. The purpose of this training was to assist the astronaut in correcting spacecraft yaw drifts. Practical experience was gained in this task by using a motorized trainer that simulated the view of the celestial sphere through the spacecraft observation window.
- 1960 February 15 - Mercury landing system and post-landing equipment tests were completed.. Spacecraft: Mercury.
- 1960 March-April - Mercury-Atlas working panels. Launch Vehicle: Atlas D.
The Mercury-Atlas working panels were reorganized into four groups: coordination, flight test, trajectory analysis, and change control. Each panel was composed of at least one representative from NASA (Space Task Group), McDonnell, Air Force Ballistic Missile Division, Space Technology Laboratory, and Convair-Astronautics.
- 1960 March - Qualification tests started on the Mercury escape tower rocket.. Spacecraft: Mercury.
These tests were completed at the end of July 1960. As a part of the qualification program, three escape-rocket motors were successfully fired on a spacecraft model at conditions corresponding to approximately 100,000 feet altitude in the Lewis Research Center altitude wind tunnel. One motor was tested on a four-component balance system to determine thrust misalignment of the rocket motor. According to test results, the rocket motor appeared to meet operational requirements.
- 1960 March 11 - Pioneer V. Spacecraft: Mercury.
Pioneer V, launched as a probe of the space between Earth and Venus, began to provide invaluable information on solar flare effects, particle energies and distributions and magnetic phenomena. Pioneer V continued to transmit such data until on June 26, 1960, when at a distance of 22.5 million miles from Earth, it established a new communications record.
- 1960 March 16 - The Space Task Group published recovery requirements for the Mercury-Atlas 1 (MA-1) flight test.. Spacecraft: Mercury. Launch Vehicle: Atlas D.
- 1960 March 28 - Mercury astronaut first open-water egress training.. Spacecraft: Mercury.
Between March 28,1960 and April 1, 1960, the astronauts received their first open-water egress training in the Gulf of Mexico off the coast of Pensacola, Florida, in cooperation with the Navy's School of Aviation Medicine. The training was conducted in conditions of up to 10-foot swells, and no problems were experienced. The average egress time was about 4 minutes from a completely restrained condition in the spacecraft to being in the life raft.
- 1960 April 29 - Agreements concluded for all overseas Mercury tracking stations.
Construction was proceeding on schedule at Cape Canaveral, Bermuda, Grand Canary Islands, the Woomera and Muchea Australian sites, and at the demonstration site on Wallops Island, Virginia. The survey of Guaymas in Western Mexico completed that phase of the program, but the construction was yet to be accomplished.
- 1960 May 9 - Beach Abort 1. Spacecraft: Mercury. Launch Site: Wallops Island.
First production model of Project Mercury spacecraft was successfully launched from NASA Wallops Station to test escape, landing, and recovery systems. Known as the "beach abort" shot, the Mercury capsule reached 775 m before parachute landing and pickup by Marine helicopter returned it to Wallops' hangar 17 minutes after launch.
- 1960 May 9 - Mercury Pad Abort 1. Spacecraft: Mercury.
McDonnell's first production spacecraft, with its escape rocket serving as the propulsion force, was launched from Wallops Island. Designated the beach-abort test, the objectives were a performance evaluation of the escape system, the parachute and landing system, and recovery operations in an off-the-pad abort situation. The test was successful.
- 1960 June 18 - Atlas launch vehicle 50-D was delivered for the first Mercury-Atlas mission (MA-1).. Launch Vehicle: Atlas D.
- 1960 June 27 - Mercury Project Orbit. Spacecraft: Mercury.
As a complement to the Mercury spacecraft reliability program, a decision was made that one production spacecraft would be withdrawn from the operational program for extensive testing. The test environment would involve vacuum, heat, and vibration conditions. This test series was later designated 'Project Orbit.'
- 1960 July 12 - Mercury astronaut desert survival training.
The astronauts underwent a five and one half day course in 'desert survival' training at the Air Training Command Survival School, Stead Air Force Base, Nevada. The possibility of an arid-area landing was remote but did exist. So this training was accomplished to supply the astronaut with the confidence and ability to survive desert conditions until recovery. The course consisted of one and one half days of academics, one day of field demonstrations, and three days of isolated remote-site training. Survival equipment normally installed in the Mercury spacecraft was used to provide the most realistic conditions.
- 1960 July 29 - Mercury MA-1. Spacecraft: Mercury. Launch Site: Cape Canaveral. Launch Vehicle: Atlas D.
Mercury-Atlas 1 (MA-1) was launched from the Atlantic Missile Range in a test of spacecraft structural integrity under maximum heating conditions. After 58.5 seconds of flight, MA-1 exploded and the spacecraft was destroyed upon impact off-shore. None of the primary capsule test objectives were met. The mission objectives were to check the integrity of the spacecraft structure and afterbody shingles for a reentry associated with a critical abort and to evaluate the open-loop performance of the Atlas abort-sensing instrumentation system. The spacecraft contained no escape system and no test subject. Standard posigrade rockets were used to separate the spacecraft from the Atlas, but the retrorockets were dummies. The flight was terminated because of a launch vehicle and adapter structural failure. The spacecraft was destroyed upon impact with the water because the recovery system was not designed to actuate under the imposed flight conditions. Later most of the spacecraft, the booster engines, and the liquid oxygen vent valve were recovered from the ocean floor. Since none of the primary flight objectives was achieved, Mercury-Atlas 2 (MA-2) was planned to fulfill the mission.
- 1960 August 3 - Redstone launch vehicle No. 1 was delivered to Cape Canaveral for the MR-1 (Mercury-Redstone).. Launch Vehicle: Redstone.
- 1960 November 8 - Mercury LJ-5. Spacecraft: Mercury. Launch Site: Wallops Island. Launch Vehicle: Little Joe.
Little Joe 5 with a Mercury production spacecraft was launched from Wallops Island to test the spacecraft in an abort simulating the most severe launch conditions. At 15.4 seconds after liftoff, the escape rocket motor and tower jettison motor ignited prematurely. Booster, capsule, and tower remained mated through ballistic trajectory until destroyed on impact.
- 1960 November 8 - Mercury Little Joe 5 (LJ-5). Spacecraft: Mercury.
LJ-5, the first of the series with a McDonnell production spacecraft, was launched from Wallops Island to check the spacecraft in an abort simulating the most severe launch conditions. The launch was normal until 15.4 seconds after lift-off, at which time the escape rocket motor was prematurely ignited. The spacecraft did not detach from the launch vehicle until impact and was destroyed. Failure to attain mission objectives was attributed to several possible causes. One of these was failure of the spacecraft-to-adpater clamp-ring limit switches. Another possibility was failure of the escape tower clamp-ring limit switches. And the third was improper rigging of the limit switches in either of those locations so that vibration or deflection could have caused switch closure. Since the test objectives were not met, a repeat of the mission was planned.
- 1960 November 21 - An attempt was made to launch Mercury-Redstone 1 (MR-1) from Cape Canaveral.. Spacecraft: Mercury. Launch Vehicle: Redstone.
This unmanned mission was unsuccessful because premature cut-off of the launch vehicle engines activated the emergency escape system when the vehicle was only about 1 inch off the pad. Engine cut-off was caused by premature loss of electrical ground power to the booster. The launch vehicle settled back on the pad with only slight damage. Since the spacecraft received a cut-off signal, the escape tower and recovery sequence was initiated. The undamaged spacecraft was recovered for reuse.
- 1960 December 19 - Mercury MR-1A. Spacecraft: Mercury. Launch Site: Cape Canaveral. Launch Vehicle: Redstone.
Mercury-Redstone 1A (MR-1A) was launched from Cape Canaveral in a repeat of the November 21, 1960, mission and was completely successful. This was the third attempt to accomplish the objectives established for this flight. The first attempt on November 7, 1960, was canceled as a result of a helium leak in the spacecraft reaction control system relief valve, and on November 21, 1960, the mission could not be completed because of premature cut-off of the launch vehicle engines. Objectives of the MR-1A flight were to qualify the spacecraft for space flight and to qualify the flight system for a primate flight scheduled shortly thereafter. Close attention was given to the spacecraft-launch vehicle combination as it went through the various flight sequences: powered flight; acceleration and deceleration; performance of the posigrade rockets; performance of the recovery system; performance of the launch, tracking, and recovery phases of the operation; other events of the flight including retrorocket operation in a space environment; and operation of instrumentation. Except that the launch vehicle cut-off velocity was slightly higher than normal, all flight sequences were satisfactory; tower separation, spacecraft separation, spacecraft turnaround, retrofire, retropackage jettison, and landing system operation occurred or were controlled as planned. The spacecraft reached a maximum altitude of 130.68 statute miles, a range of 234.8 statute miles, and a speed of 4,909.1 miles per hour. Fifteen minutes after landing in the Atlantic Ocean, the recovery helicopter picked up the spacecraft to complete the successful flight mission.
- 1961 January 31 - Mercury MR-2. Spacecraft: Mercury. Launch Site: Cape Canaveral. Launch Vehicle: Redstone.
Ham, a 37-pound chimpanzee, was aboard the spacecraft. The over-acceleration of the launch vehicle coupled with the velocity of the escape rocket caused the spacecraft to attain a higher altitude and a longer range than planned. In addition, the early depletion of the liquid oxygen caused a signal that separated the spacecraft from the launch vehicle a few seconds early. However spacecraft recovery was effected, although there were some leaks and the spacecraft was taking on water. Ham appeared to be in good physiological condition, but sometime later when he was shown the spacecraft it was visually apparent that he had no further interest in cooperating with the space flight program. Despite the over-acceleration factor, the flight was considered to be successful.
- 1961 February 21 - Mercury MA-2. Spacecraft: Mercury. Launch Site: Cape Canaveral. Launch Vehicle: Atlas D.
Mercury-Atlas 2 (MA-2) was launched from Cape Canaveral in a test to check maximum heating and its effects during the worst reentry design conditions. The flight closely matched the desired trajectory and attained a maximum altitude of 114.04 statute miles and a range of 1,431.6 statute miles. Inspection of the spacecraft aboard the recovery ship some 55 minutes after launch (actual flight time was 17.56 minutes) indicated that test objectives were met, since the structure and heat protection elements appeared to be in excellent condition. The flight control team obtained satisfactory data; and the complete launch computing and display system, operating for the first time in a flight, performed satisfactorily.
- 1961 February 21 - First Mercury crews selected..
NASA Space Task Group selected John H. Glenn, Jr., Virgil I. Grissom, and Alan B. Shepard, Jr., to begin special training for first manned Mercury space flight.
- 1961 February 25 - Successful drop test using Mercury boilerplate.. Spacecraft: Mercury.
McDonnell conducted a successful drop test, using a boilerplate spacecraft fitted with impact skirt, straps and cables, and a beryllium heat shield. During the tests the stainless steel straps were successfully stretched to design limits.
- 1961 March 18 - Mercury LJ-5A. Spacecraft: Mercury. Launch Site: Wallops Island. Launch Vehicle: Little Joe.
Mercury Little Joe 5A (LJ-5A), the sixth in the series of Little Joe missions, was launched from Wallops Island. This flight was intended to satisfy test objectives, which were not met previously because of the failure of the spacecraft to separate from the launch vehicle during the Little Joe 5 (LJ-5) mission flown on November 8, 1960. For reference, the purpose of this test was to demonstrate primarily the structural integrity of the spacecraft and the escape system during an escape maneuver initiated at the highest dynamic pressure anticipated during an Atlas launch for orbital flight. Little Joe 5A (LJ-5A) lifted off normally, but 19 seconds later the escape tower fired prematurely, a situation closely resembling the November 1960 flight. The signal to initiate the abort maneuver was given; and the launch vehicle-adapter clamp ring was released as intended, but the spacecraft remained on the launch vehicle since the escape motor was already expended. The separation was effected by using the retrorockets, but this command was transmitted before the flight had reached its apex, where separation had been planned. Therefore, the separation was rather violent. The parachutes did deploy at about 40,000 feet, and after recovery it was found that the spacecraft had actually incurred only superficial structural damage. In fact, this spacecraft was later used for the subsequent Little Joe 5B (LJ-5B) flight test. Test objectives of the Little Joe 5A (LJ-5A) were not met.
- 1961 March 20 - Phase III of the Mercury spacecraft airdrop program. Spacecraft: Mercury.
Primary objectives of the drops were to study further the spacecraft suitability and flotation capability after water impact. Six drops were made, but later (April 24-28, 1961) the tests were extended for two additional drops to monitor hard-surface landing effects. In the water phase of the program, spacecraft components under particular scrutiny were the lower pressure bulkhead and its capability to withstanding heat shield recontact without impairing flotation capability. Helicopters were used to make the drops.
- 1961 March 24 - Mercury MR-BD. Spacecraft: Mercury.
After analyzing launch vehicle behavior in the Mercury-Redstone 1A (MR-1A) and Mercury-Redstone 2 (MR-2), officials at the Marshall Space Flight Center and the Space Task Group were of the opinion that there were a number of problems that needed to be corrected prior to the advent of manned flight. The problems to be resolved included jet-vane vibration, instrumentation compartment vibration, failure of the thrust-controller system, and several other areas that needed attention. Many of these problems were studied by the personnel of engineering activities and proposed solutions were formulated. It was felt, however, that flight was necessary to verify the corrections and the Mercury-Redstone Booster Development test was scheduled and flown. All test objectives were met; as a result of this test, the launch vehicle was man-rated for the planned suborbital flights.
- 1961 March 24 - Mercury MR-3A (cancelled). Spacecraft: Mercury.
After booster problems on the Mercury MR-2 chimp test flight, Von Braun insisted on a further unmanned booster test flight, against the wishes of Shepard and others at NASA. A Mercury boilerplate capsule was launched on a flawless test on 24 March. If NASA had overruled Von Braun, the manned Freedom 7 capsule would have flown instead. Shepard would have been the first man in space (though not in orbit), beating Gagarin's flight by three weeks.
- 1961 April 25 - Mercury MA-3. Spacecraft: Mercury. Launch Site: Cape Canaveral. Launch Vehicle: Atlas D.
Mercury-Atlas 3 (MA-3) was launched from Cape Canaveral in an attempt to orbit the spacecraft with a 'mechanical astronaut' aboard. After lift-off, the launch vehicle failed to roll to a 70 degree heading and to pitch over into the proper trajectory. The abort-sensing system activated the escape rockets prior to the launch vehicle's destruction by the range safety officer after approximately 40 seconds of flight that had attained an altitude of 16,400 feet. The spacecraft then coasted up to 24,000 feet, deployed its parachutes, and landed in the Atlantic Ocean 2,000 yards north of the launch pad. The spacecraft was recovered and was found to have incurred only superficial damage; it was then shipped to McDonnell for refitting.
- 1961 April 28 - Mercury LJ-5B. Launch Site: Wallops Island. Launch Vehicle: Little Joe.
Little Joe 5B (LJ-5B) was launched from Wallops Island to test the Mercury escape system under maximum dynamic pressure conditions. At the time of lift-off, one of the launch vehicle rocket motors did not ignite until after 4 seconds had elapsed. This delay caused the launch vehicle to pitch into a lower trajectory than had been planned, with a result that the abort maneuver experienced greater dynamic pressures than had been specified in the flight test plan. Other than this, all other sequential systems operated according to plan, and after landing, a normal helicopter recovery was accomplished. Thus, all test objectives were met and were actually exceeded because the spacecraft withstood the higher dynamic pressures.
- 1961 May 1 - Webb warns of Mercury failures.. Launch Vehicle: Redstone.
NASA Administrator Webb issued a statement concerning the 2-year Mercury manned space flight program, which said, in part: "NASA has not attempted to encourage press coverage of the first Mercury-Redstone manned flight. It has responded to press and television requests, with the result that over 100 representatives of the press, radio, and TV are now at Cape Canaveral. . . . We must keep the perspective that each flight is but one of the many milestones we must pass. Some will completely succeed in every respect, some partially, and some will fail. From all of them will come mastery of the vast new space environment on which so much of our future depends."
- 1961 May 5 - Mercury MR-3. Spacecraft: Mercury. Mass: 1,290 kg (2,840 lb). Launch Site: Cape Canaveral. Launch Vehicle: Redstone.
Alan Shepard first American in space, less than a month after Gagarin and only on a 15 minute suborbital flight. Only manned flight with original Mercury capsule design (tiny round porthole and periscope a la Vostok). If NASA had not listened to Von Braun, Shepard would have flown on the MR-BD flight of 24 March, beating Gagarin by three weeks and becoming the first man in space (though not in orbit). Shepard's capsule reached an altitude of 115.696 miles, range of 302 miles,and speed of 5,100 miles per hour. He demonstrated control of a vehicle during weightlessness and high G stresses. Recovery operations were perfect; there was no damage to the spacecraft; and Astronaut Shepard was in excellent condition.
- 1961 May 9 - Kennedy decision to allow MR-3 flight defended.. Launch Vehicle: Redstone.
Senator Robert S. Kerr, chairman of the Senate Aeronautical and Space Sciences Committee, told a group at the National Radio and Television Convention that President Kennedy accepted the views of NASA and congressional leaders in approving the manned Mercury-Redstone flight of May 5.
- 1961 May 26 - Mercury Freedom 7 at Paris Air Show.. Spacecraft: Mercury.
Until June 4, 1961, the Mercury spacecraft Freedom 7 (MR-3) was displayed at the Paris International Air Show. Some 650,000 visitors received the details on the spacecraft and on Shepard's suborbital flight.
- 1961 May 26 - Freedom 7 displayed at Paris Air Show.. Spacecraft: Mercury.
Freedom 7, Mercury spacecraft in which Alan B. Shepard, Jr., made his space flight on May 5, was a major drawing card at the Paris International Air Show. Details of the spacecraft and of Shepard's flight were related to about 650,000 visitors.
- 1961 June 1 - Prelaunch mission rules for Mercury-Atlas 4 (MA-4) were published.. Launch Vehicle: Atlas D.
- 1961 June 8 - Mercury-Atlas 4 (MA-4) recovery requirements were published.. Launch Vehicle: Atlas D.
- 1961 July 21 - Mercury MR-4. Spacecraft: Mercury. Mass: 1,286 kg (2,835 lb). Launch Site: Cape Canaveral. Launch Vehicle: Redstone.
The Mercury capsule, Liberty Bell 7, manned by Astronaut Virgil I. Grissom, boosted by a Redstone rocket, reached a peak altitude of 190.3 km and a speed of 8,335 km per hour. After a flight of 15 minutes and 37 seconds, the landing was made 487 km downrange from the launch site. The hatch blew while still in water, and the capsule sank; Grissom saved, though his suit was filling up with water through open oxygen inlet lines.
This was the second and final manned suborbital Mercury Redstone flight, and the first flight with trapezoidal window. Further suborbital flights (each astronaut was to make one as a training exercise) were cancelled. An attempt to recover the capsule in very deep water in 1994 not successful. It was finally raised in the summer of 1999.
- 1961 July 27-28 - Advanced Mercury concepts. Spacecraft: Mercury Mark I, Gemini.
After the 2-man space concept (later designated Project Gemini) was introduced in May 1961, a briefing between McDonnell and NASA personnel was held on the matter. As a result of this meeting, space flight design effort was concentrated on the 18-orbit 1-man Mercury and on a 2-man spacecraft capable of advanced missions.
- 1961 August 24 - Mercury-Atlas 4 (MA-4) unmanned orbital flight was postponed.. Launch Vehicle: Atlas D.
- 1961 August 30 - Investigation of the Mercury MR-4 explosive egress hatch.. Spacecraft: Mercury. Launch Vehicle: Redstone.
An investigation was conducted as a result of the premature activation of the Mercury-Redstone 4 (MR-4) explosive egress hatch. Tests were initiated in an environment more severe than had been conducted in prelaunch activities and tests, but no premature firings occurred. As a backup, McDonnell was asked to design a mechanical-type hatch. The model weighed some 60 pounds more than the explosive type, so other methods had to be sought to prevent any recurrence of the incident. A procedure was initiated which stipulated that the firing plunger safety pin would be left in place until the helicopter hook was attached to the spacecraft and tension was applied to the recovery cable.
- 1961 September 5, 9 and 14 - Mercury rocket sled tests. Spacecraft: Mercury.
Three rocket sled tests were conducted at the Naval Ordnance Test Station, China Lake, California, to study the detailed launch vehicle-spacecraft, clamp-ring separation. From run to run, minor modifications were made, and by the third run the separation action was perfected.
- 1961 September 13 - Mercury MA-4. Spacecraft: Mercury. Mass: 1,200 kg (2,600 lb). Launch Site: Cape Canaveral. Launch Vehicle: Atlas D.
Mercury-Atlas 4 (MA-4) was launched from Cape Canaveral with special vibration and noise instrumentation and a mechanical crewman simulator aboard in addition to the normal spacecraft equipment. This was the first Mercury spacecraft to attain an earth orbit. The orbital apogee was 123 nautical miles and the perigee was 86 nautical miles. After one orbit, the spacecraft's orbital timing device triggered the retrograde rockets, and the spacecraft splashed in the Atlantic Ocean 161 miles east of Bermuda. Recovery was made by the USS Decatur. During the flight, only three slight deviations were noted - a small leak in the oxygen system; loss of voice contact over Australia; and the failure of an inverter in the environmental control system. Overall, the flight was highly successful: the Atlas booster performed well and demonstrated that it was ready for the manned flight, the spacecraft systems operated well, and the Mercury global tracking network and telemetry operated in an excellent manner and was ready to support manned orbital flight.
- 1961 September 18 - Mission rules for the Mercury-Atlas 5 (MA-5) orbital flight.. Launch Vehicle: Atlas D.
Mission rules for the Mercury-Atlas 5 (MA-5) orbital flight were published. Revisions were issued on October 16 and 25, 1961, and November 11, 1961.
- 1961 September 24 - NASA reorganization.
NASA Administrator Webb announced major organizational changes and top-level appointments to become effective November 1. The reorganization should provide a clearer focus on major programs and allow center directors to have a louder voice in policy making. The new appointments included the following Directors of major program offices: Ira H. Abbott, Office of Advanced Research and Technology; Homer E. Newell, Office of Space Sciences; D. Brainerd Holmes, Office of Manned Space Flight; and an as yet unnamed Director of Office of Applications Programs. Also, Thomas F. Dixon was appointed Deputy Associate Administrator; Abe Silverstein was named Director of the Lewis Research Center, and Robert R. Gilruth was chosen Director of the Manned Spacecraft Center.
- 1961 October 23 - Freedom 7 deposited in Smithsonian.. Spacecraft: Mercury.
The Freedom 7 Mercury capsule in which Alan B. Shepard, Jr., made the first suborbital space flight, was presented to the National Air Museum of the Smithsonian Institution. In his presentation, NASA Administrator Webb said: "To Americans seeking answers, proof that man can survive in the hostile realm of space is not enough. A solid and meaningful foundation for public support and the basis for our Apollo man-in-space effort is that U.S. astronauts are going into space to do useful work in the cause of all their fellow men."
- 1961 November 1 - Mercury MS-1. Spacecraft: Radio Test Spacecraft. Launch Site: Cape Canaveral. Launch Vehicle: Blue Scout 2.
Small satellite was to have verified the readiness of the worldwide Mercury tracking network. An attempt was made to launch Mercury-Scout 1 (MS-1) into orbit with a communications package further to qualify the radar tracking of the Mercury global network prior to manned orbital flight. Shortly after lift-off, the launch vehicle developed erratic motions and attending high aerodynamic loads, and was destroyed by the Range Safety Officer after 43 seconds of flight. No further attempts were planned. The Mercury-Atlas 4 (MA-4) mission and the successful Mercury-Atlas 5 (MA-5), flown on November 29, 1961, disclosed that the network met all requirements.
- 1961 November 12 - Mercury 5 launch postponed. Spacecraft: Mercury. Launch Vehicle: Atlas D.
Mercury-Atlas 5, scheduled for launch no earlier than November 14, ran into technical difficulties, postponing launch for several days.
- 1961 November 29 - Mercury MA-5. Spacecraft: Mercury. Mass: 1,300 kg (2,800 lb). Launch Site: Cape Canaveral. Launch Vehicle: Atlas D.
Mercury-Atlas 5 (MA-5), the second and final orbital qualification of the spacecraft prior to manned flight was launched from Cape Canaveral with Enos, a 37.5 pound chimpanzee, aboard. Scheduled for three orbits, the spacecraft was returned to earth after two orbits due to the failure of a roll reaction jet and to the overheating of an inverter in the electrical system. Both of these difficulties could have been corrected had an astronaut been aboard. The spacecraft was recovered 255 miles southeast of Bermuda by the USS Stormes. During the flight, the chimpanzee performed psychomotor duties and upon recovery was found to be in excellent physical condition. The flight was termed highly successful and the Mercury spacecraft well qualified to support manned orbital flight.
- 1961 November 29 - Glenn selected for the first Mercury manned orbital flight..
Astronaut John Glenn was selected as the pilot for the first Mercury manned orbital flight, with Scott Carpenter as backup pilot. Immediately, training was started to ready these two astronauts for the mission. The five remaining astronauts concentrated their efforts on various engineering and operational groups of the Manned Spacecraft Center in preparation for the mission.
- 1961 December 7 - Mercury manned orbital flight postponed.. Spacecraft: Mercury.
NASA postponed its projected manned orbital flight from December 1961 until early in 1962 because of minor problems with the cooling system and positioning devices in the Mercury capsule, Dr. Hugh Dryden, Deputy Administrator of NASA, said in a Baltimore interview. "You like to have a man go with everything just as near perfect as possible. This business is risky. You can't avoid this, but you can take all the precautions you know about."
| |